of both

Section 3 • Installation

of both

Check the ability of the soil to carry the load

Check wet season and dry season soil characteristics for static loading limits and elasticity

Check local codes for Seismic Design requirements

For examples of foundation diagrams, see to Figure 3-2 and Figure 3-3.

trolled level and a surface texture etched in place. Leave the concrete to cure for at least 28 days.

Compressor Unit Installation

Once the foundation has cured, the compressor unit can be placed on the foundation, see Figure 3-5 and Figure 3-6. With the appropriate material handling equipment, lift the compressor unit by locations shown on the Vilter GA drawing and slowly place it on the

G.A.

G.A.

COMPRESSOR UNIT

CENTER LINE OF

GAS COMPRESSION

SYSTEM

 

CLR.

EL. TOP OF

(TYP.)2"

(TYP.)2"

 

GRADE

 

2"

 

 

 

0"

6"

 

 

 

1'-

 

 

 

 

 

CLR.

 

# 6 @ 12"

 

 

 

EACH WAY

 

 

3"

 

 

 

 

TOP & BOTTOM

 

 

 

 

 

4" COMPACTED SAND

Compressor Unit Installation EXCAVATE TO FROST DEPTH AS REQ'D AND BACKFILL

WITH CLSM OR NON-FROST SUSCEPTIBLE FILL

Figure 3-2. Concrete Pad with Compressor Unit Dimensions - Side View

NOTE

In Figures 3-3 and 3-8, the recommended housekeeping height of 6” is to allow maintenance/ service of the oil strainer and oil pump.

Once the site has been excavated and prepared, place four inches of sand down on the bed where the founda- tion will rest. The sand must be compacted before plac- ing the forms and rebar. After the sand is compacted, use the Vilter GA drawing to construct the forms for the foundation. With forms in place, install expansion boards on the inside of the forms, for example, see Figure 3-4. Next, place your rebar in the forms as per the Vilter foundation drawing. When all rebars are in place the concrete can be poured. The concrete must then be

foundation housekeeping piers. As per the Vilter GA drawing, ensure the compressor unit is correctly placed on the foundation. Once placed, use the spherical wash- ers directly under the compressor as the surface to level the compressor unit, see Figure 3-7. Place shims under the feet of the compressor unit, as needed, until it is leveled, see Figure 3-8. Select the correct drill bit and drill thru the anchor bolt hole in the mounting feet of the compressor unit to the depth called for on the Vilter foundation drawing. Finally using the HILTI instructions, put your anchor bolts in place and wait for them to cure. Then place the nuts on the anchor bolts to finger tight and prepare to grout.

3 – 6

VSG/VSSG • Installation, Operation and Maintenance Manual •Vilter/Emerson • 35391SSG

Page 26
Image 26
Emerson VSSG, VSG manual Compressor Unit Installation, of both Check the ability of the soil to carry the load