Emerson VSSG, VSG manual Installation Pre Start-Up, Pre Start-Up Checklist

Models: VSG

1 106
Download 106 pages 24.52 Kb
Page 42
Image 42
Section 3 • Installation

Section 3 • Installation

Pre Start-Up

The following check list is to help prepare the equipment before the Vilter technician arrives at the jobsite. Vilter recommends that a trained technician go through the following tasks. The operating manuals provided by Vilter can be referenced for any type of questions or special instructions.

Every gas compressor unit includes a Vilter start-up (confirm on P.O.). The following tasks are not included in the Vilter start-up provided in your equipment purchase. Any tasks below that are done by the Vilter technician will take away from the pre-determined time that was provided with the equipment purchase. Vilter suggests that the Vilter technician’s time be used during the start-up of the system and not for the below system preparation.

NOTICE

Each item below must be checked-off, signed and returned to Vilter Service Department. Failure to do so will “Null & Void” future warranty considerations.

Pre Start-Up Checklist

Name (Please Print):

 

 

Signature:

 

 

 

Company:

 

 

Vilter Sales Order Number:

 

Equipment Description:

 

Date (M/D/Y):

 

1. The unit should be leveled and secured to the concrete pad foundation.

2. Proper electric supply and grounding need to be supplied to the unit. All power and control lines should be wired to unit. Electric supply to be verified at each device requiring power.

3. Verify any type of level switches that are on a vessel before the compressor are hardwired and able to shut off the compressor (should be wired to “Aux” on micro-controller and starter).

4. The suction and discharge line must be piped and properly supported independent of the unit.

5. The discharge stop and check valve is shipped loose and must be installed. During off periods, liquid can condense in the line downstream of the discharge stop and check valve. It is recommended that the stop and check valve be located horizontally to minimize the quantity of liquid that can accumulate downstream of the check valve.

6. A dual safety relief valve is shipped loose for field installation. A connection is provided on the oil separator for the relief valve. Refer to ASME Code for proper sizing of relief valves and vent lines.

7. On water cooled oil coolers, the water lines must be connected to the front head of the oil cooler. Water regulating and solenoid valves are recommended.

(Continued on next page)

3 – 22

VSG/VSSG • Installation, Operation and Maintenance Manual •Vilter/Emerson • 35391SSG

Page 42
Image 42
Emerson VSSG, VSG manual Installation Pre Start-Up, Pre Start-Up Checklist