Finalizing the Installation (for qualified installers only) | 47 |
Power Heat Duct Installation
The optional power heat duct may be used with this fireplace. Refer to the part numbers below if you wish to insta this accessory. Instructions are includ with the power heat duct.
•Power Heat Duct (98500769)
•1080/36
NOTE: The power heat duct must be attached at the time of firepla installation.
Andiron Installation
|
| Floor | |
Junction Box |
| Boot | |
| Maximum Duct | ||
|
| Length = 20' | |
Rheostat |
|
| |
(with cover plate) |
|
| |
Use 10” x |
| Blower | |
| Box | ||
wall stack (duct) |
| ||
|
| ||
when passing |
| Duct Adapter | |
through tight |
| (6” Round to 10” x | |
areas. |
| 6" Duct | |
|
| ||
|
| Starter Ring | |
|
| Heat Duct | |
Grill |
| Electrical | |
Wall Adapter | Wiring | ||
| |||
| (for use on |
| |
| 2 x 4 walls) |
| |
|
| Electrical | |
|
| Source |
This fireplace includes four andiron brackets that allow for use of the optional andirons. Follow the directions below if installing andirons. NOTE: The firebacks should be installed prior to installing the andirons.
1The andiron clip attaches to the front of the burner (there are two on each side for a total of four). Remove the screw and attach the clip. NOTE: the firebacks are not pictured in the pictures.
2Secure the andiron to the clip with the bolts included with the andirons. We recommend you
© Travis Industries | 4090102 |