1. INSTALLATION

1.3Distributor Unit DS-610

The distributor unit can be mounted on the deck or on a bulkhead. Consider the following points when selecting a mounting location.

Select a location which is both well ventilated and low in humidity to keep the unit cool.

For bulkhead mounting, be sure the mounting location is strong enough to support the weight under the continued vibration normally encountered on the vessel.

A magnetic compass will be affected if the distribution box is too close. Observe the compass safe distances to prevent disturbance to the magnetic compass.

1.Screw in lower hex. bolts so there is 5 mm clearance between bottom of screw head and bulk- head.

2.Hang the unit on the bolts, then tighten the bolts.

3.Fasten the unit with upper hex. bolts.

620±1 (24.41”)

Fixing hole 2- 12

450±1 (17.72”) 98 (3.86”)

(37) (1.46”)

630 (24.80”)

12 (0.47”)

1-5

Page 11
Image 11
Furuno DS-60 installation manual Distributor Unit DS-610