A. Appliance Preparation

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

1.Remove seal cap by lifting up and off of the starting collar.

2.Place first twelve inch vent section on the starting collar.

WARNING! Risk of Fire! A MINIMUM of twelve inches verti- cal pipe is required prior to attaching any elbow to the appli- ance.

3.Place fiberglass rope ring over initial twelve inch vent section and position tightly to top of appliance.

4.Remove bottom metal panel by removing four screws. Screw locations are shown in Figure 9.1. The two screws on the bottom side are located behind the panel. Remove all four screws and gently lift the panel off the appliance avoiding contact with the non-combustible board if possible.

FIBERGLASS ROPE RING

BOTTOM PANEL SCREW LOCATIONS

Figure 9.1 Location of Fiberglass Rope Ring

Heat & Glo • RED40, RED40ST • 2155-900 Rev. o • 7/12

35

 

Page 35
Image 35
Heat & Glo LifeStyle RED40ST owner manual A. Appliance Preparation