Installation Guide - Overview
Table 10 - Site and Equipment Preparation
Step |
| Procedure |
| Reference |
|
|
| ||
1 | Referring to Site Planning Documentation, ensure that | Site Planning Documentation | ||
| sufficient numbers of the following items are on hand: | In this Manual: | ||
| • Racks | |||
| • Section on | |||
|
|
| ||
| • Power Supplies (1 per rack) |
| Planning. | |
| • Controller Module or Scanner (1 per rack) | • | Sections on installation | |
| • I/O Modules (correct type for each configured slot) | • | Appendix A | |
| • Terminal Blocks, Barrier or Euro style, (1 for each I/O |
|
| |
| Module) |
|
| |
| • Jumpers |
|
| |
| Terminal Blocks) |
|
| |
| • Tie Wraps (1 or 2 for each Terminal Block) |
|
| |
| • I/O Label (one per terminal block, by module type) |
|
| |
| • Filler Block Cover (1 for each slot not occupied by an |
|
| |
| I/O Module) |
|
| |
| • Blank label (1 for each Filler Block Cover) |
|
| |
| • Grounding Bars for I/O wiring shields (1 or 2 for each 4- |
|
| |
| slots in each rack) |
|
| |
| • Wiring terminal lugs (for connecting I/O shields to |
|
| |
| grounding bars) |
|
| |
| • Sheet metal screws, steel #10 or M4, for mounting racks |
|
| |
| in enclosures (4 screws for |
|
| |
|
|
| ||
|
|
| ||
2 | Install (or verify correct installation of) enclosures for HC900 | Site Plan Documentation and | ||
| Controllers and ancillary equipment: | this section of this manual | ||
| • Mounting rails or |
|
| |
| • (for cabinet with multiple HC900 Chassis): |
|
| |
| − | grounding bus |
|
|
| − | barrier strip for AC power |
|
|
| • Master control Relay |
|
| |
|
|
| ||
3 | Install (or verify correct installation of) enclosures ("closets") | Appendix A. | ||
| for networking devices: | Note : Some networking | ||
|
|
| ||
|
|
| devices may share enclosures | |
|
|
| with HC900 Controller | |
|
|
| components. | |
|
|
|
|
|
50 | HC900 Hybrid Controller Installation and User Guide | Revision 5 |
|
| 9/03 |