5.Close the main breaker in the House panel on the exterior of the HP POD.

6.Close the remaining breakers in the House panel one by one, following the panel schedule on the inside of the House panel.

NOTE: If you are installing a high density HP POD, you must also close the main breaker in the electrical busway 3 panel.

7.Close the main breakers in the electrical busway 1 and electrical busway 2 panels.

8.Inside the HP POD, close the breaker on each drop box that is connected to a rack of IT components.

9.Power up your remaining racks and IT components following your standard IT startup procedure.

Commissioning the HP POD

Commissioning your HP POD is an optional service and is customized based on your facility. A typical commissioning process includes the following tests:

Tighten the electrical busway connections

Verify accurate electrical installation

Verify accurate mechanical installation

Test the operation of the BMS and Cooling controls

Test the operation of the smoke detection system

Test the operation of EPO system

Installation 25