Item

Component

Description

 

 

 

4

ASSD panel (on page 36)

Air sampling smoke detection system

 

 

 

5

EPO button

Cuts off all power to the POD and activates the EPO alarm

 

 

lamp.

 

 

 

6

Security panel ("Security panel

Reserved for installing interface and power requirements for

 

location" on page 39)

any optional security devices installed.

 

 

 

7

EPMS panel("EPMS panel"

Electrical power monitoring system

 

on page 38)

 

 

 

 

8

Humidifier ("Humidifier

Maintains the humidity inside the HP POD within a set range

 

(optional)" on page 44)*

to minimize static electricity.

 

 

 

9

Auxiliary Land power*

Provides auxiliary power for the BMS or convenience outlets.

 

 

120V owner-provided power.

 

 

 

10

BMS panel (on page 36)

Building Management System

 

 

 

11

Fan control (FC) panel ("Fan

Circuit breakers that control the fan units

 

control panel" on page 38)

 

 

 

 

12

House panel (on page 38)

120A electrical panel board providing auxiliary HP POD

 

 

electrical requirements

 

 

 

13

Junction Box

Main input box for incoming electrical feeder cables

 

 

 

Optional component

Transformer and switchboard components (optional)

NOTE: The transformer and switchboard must be a minimum of 1.2 m (48 in) away from the

HP POD.

Item

Component

Description

 

 

 

1

Switchboard

Distributes power to each of the

 

 

electrical busways breakers and the

 

 

House panel

 

 

 

Component identification 15