Each external panel is secured through key lock hardware.

The following locations have been prewired for your own security upgrades.

Callout

Description

 

 

1

Prewired junction box locations

 

 

2

Card reader locations

 

 

3

Internal camera locations

 

 

4

External camera locations

 

 

Transformers and switchboards

HP offers several transformers and switchboards to supply your power needs.

On-site connections include:

From your main facility power to the primary side of the transformer

From the transformer to the switchboard

From the feeder breaker lugs within the switchboard assembly to the HP POD

The standard cables should allow for placing the transformer and switchboard approximately 3.0 m (10 ft) away from the HP POD. Installation costs assume that connections are within the 3.0 m (10 ft) recommendation. If you place the transformer and switchboard more than 3.0 m (10 ft) away from the HP POD, additional planning and costs are involved.

Water distribution kit

HP recommends using the optional water distribution kit to provide water to your HP POD. For more information about the kit, see Water distribution kit components ("Water distribution kit components (optional)" on page 16).

NOTE: The water distribution kit pipes are flushed prior to shipment.

The water distribution kit is enclosed within a 10 ft ISO container that includes internal lighting and heating. The heater comes equipped with a programmable thermostat that you can set to run as needed to ensure the water temperature inside does not drop below freezing.

Optional components 45