Cooling water

Power

Drain (optional)

Available to connect to central facility infrastructure

BMS via BacNet protocol

Security system

Convenience outlet power

Site networking connection

Domestic water for humidifier (optional)

Transformer, switchboard, and water distribution kit locations

If you choose to purchase the kits, consider:

Distance from the facility utilities

Distance from the HP POD

The transformer and switchboard can be installed within 3 m (10 ft) of the HP POD during normal installation. The transformer and switchboard can be installed over 3 m (10 ft) from the HP POD, but this requires additional planning and costs. HP recommends installing the transformer and switchboard no more than 30 m (98 ft) from the HP POD.

The water distribution kit can be installed within 3 m (10 ft) of the HP POD during normal installation. The water distribution kit can be installed over 3 m (10 ft) from the HP POD, but this requires additional planning and costs. HP recommends installing the water distribution kit no more than 30 m (98 ft) from the HP POD.

HP POD connection locations

Callout

Connection

 

 

1

Main input power junction box

 

 

Site requirements 7

Page 7
Image 7
HP Performance Optimized Data Center (POD) 40cp manual Available to connect to central facility infrastructure