•Cooling water
•Power
•Drain (optional)
Available to connect to central facility infrastructure
•BMS via BacNet protocol
•Security system
•Convenience outlet power
•Site networking connection
•Domestic water for humidifier (optional)
Transformer, switchboard, and water distribution kit locations
If you choose to purchase the kits, consider:
•Distance from the facility utilities
•Distance from the HP POD
The transformer and switchboard can be installed within 3 m (10 ft) of the HP POD during normal installation. The transformer and switchboard can be installed over 3 m (10 ft) from the HP POD, but this requires additional planning and costs. HP recommends installing the transformer and switchboard no more than 30 m (98 ft) from the HP POD.
The water distribution kit can be installed within 3 m (10 ft) of the HP POD during normal installation. The water distribution kit can be installed over 3 m (10 ft) from the HP POD, but this requires additional planning and costs. HP recommends installing the water distribution kit no more than 30 m (98 ft) from the HP POD.
HP POD connection locations
Callout | Connection |
|
|
1 | Main input power junction box |
|
|
Site requirements 7