Leveling requirements

The site location for the HP POD must be level +/- 0.5 degree tolerance.

Grounding requirements

IMPORTANT: Before installing the HP POD, consult your local AHJ for applicable codes and to review site-specific location guidelines.

The HP POD must be grounded in accordance to local electric code. HP recommends grounding the HP POD, the transformer and switchboard, and the water distribution kit to your ground grid system for full protection.

Lightning protection

If the HP POD is installed in an outdoor environment, HP recommends hiring a lightning protection consultant to evaluate potential lightning risks and assess possible HP POD lightning protection schemes.

Component documentation

The Operations and Maintenance Manual, that includes all contractor-installed component documentation and all server and IT equipment documentation is delivered with your HP POD.