Alarm

Meaning

Solution

 

 

 

Fan failure

One of the fans is not working.

If you are still within your service

 

 

contract, contact HP service.

 

 

 

Sensor failure

One of the sensors is not working.

If you are still within your service

 

 

contract, contact HP service.

 

 

 

Leak detection

The drain tray senses water.

Turn off the water flowing into your HP

 

 

POD at the facility line. Turn off all IT

 

 

components, so that the components do

 

 

not overheat. If you are still within your

 

 

service contract, contact HP service.

 

 

 

Change filter*

The return air filters are full.

Replace the return air filters.

 

 

 

High temperature

The cold aisle temperature has

Check to make sure that you have

 

surpassed the set point temperature.

water flowing into your HP POD and

 

 

that the fans are blowing. If you are still

 

 

within your service contract, contact HP

 

 

service.

 

 

 

Low temperature

The cold aisle temperature is too low.

Check you HP POD components to

 

 

make sure all components are

 

 

operating as normal. If you are still

 

 

within your service contract, contact HP

 

 

service.

 

 

 

EPO

Someone has activated the EPO

Follow emergency procedures.

 

system and shut down the HP POD.

After the emergency is cleared, reset

 

 

 

 

the EPO and other HP POD systems.

 

 

 

*The change filter alarm is only relayed to your BMS if you have the optional filter replacement sensor installed.

Safety and security alarms

Alarms pertaining to the safety of the HP POD are (optionally) relayed through your building fire and security dispatch.

Alarm

Meaning

Solution

 

 

 

Fire alarm*

A fire has been detected in the HP

Activate the EPO. Follow emergency

 

POD.

procedures for your facility.

 

 

 

Security alarm

There has been a security breach.

Follow emergency procedures for your facility.

(optional)

 

 

 

 

 

EPO

Someone has activated the EPO

Follow emergency procedures for your facility.

 

system and shut down the HP POD.

 

 

 

 

*The fire alarm is only relayed to your building fire and security dispatch if you have connected your facility to the fire alarm panel.

Fire alarm sequence of operations

If a fire alarm or manual pull station is activated, the HP POD follows this sequence of operations.

1.The HP POD sends an alarm signal to the building fire and security dispatch.

2.The AC unit shuts down.

3.The HP POD security lights flash and the horns sound the 30-second evacuation alarm.

Building management system 42

Page 42
Image 42
HP Performance Optimized Data Center (POD) 40cp manual Safety and security alarms, Fire alarm sequence of operations