3.Pump domestic or industrial water into the water distribution kit closed-loop system fill tank, according to the water quality requirements (on page 30).

NOTE: The HP POD pipe design is rated for a maximum pressure rating of 150 psi.

4.Verify that your facility water pressure is within the acceptable range (20-25 psi).

5.Initiate the system pumps on the water distribution kit:

o Manually initiate the system pumps with the main power switch located on the pumps.

- or -

oConnect the water distribution kit to the BMS system, and initiate the system pumps through the BMS.

Installation 20