Positioning via a CC-Link Network | CC-Link Communication Settings |
| |
5.2.2Configuration for communication with GX IEC Developer
Generally, positioning control is performed via a CC-Link network in applications where an additional PLC system is used for automation tasks as well as the integrated controller in the ampli- fier. In this example we will thus only provide detailed descriptions of the settings required to integrate the servo amplifier in your project.
Procedure:
How to open an existing project in GX IEC Developer:
Select Network in the project directory tree in the left window.
Select CC-Link in the Network Parameter box.
This opens the window Network parameters: Setting the CC-Link list where you can now enter the settings shown in Fig. 5-6.
(c)
Fig. 5-6:Settings required in GX IEC Developer for CC-Link communication between the controller and the servo amplifier