Chapter 3. Operation

ASM-20Installation and Operation Manual

 

 

Activation of Tests

Operational

Jumper and

Switch Changes

Warning

In order to verify that the ASM-20 is operating correctly, use the internal BERT and analog loopback tests as described in Bit Error Rate Tester (BERT) in Chapter 4 and Local Test - Analog Loopback in Chapter 4.

If you need to reconfigure the ASM-20 for a different type of operation, the jumpers and switches must be changed to correspond to the new operating mode.

Only authorized or qualified personnel should have access inside the equipment. Disconnect the ASM-20 power cable before opening the top cover.

For guidance in repositioning the jumpers and switches, refer to Electrical Installation in Chapter 2. The equipment will become unsafe for connection to telecommunication networks in some locations, if the signal ground is disconnected from the chassis ground.

Power Off

To turn off the AC power to the ASM-20, simply remove the AC power cord

Procedure

from the AC source.

3-4 Operating Instructions