Chilled-Water System Design
notes
chillers piped in series
Staggered Set Points
set point =48°F[8.9°C] | set point =42°F[5.6°C] |
42°F
48°F[5.6°C] [8.9°C]
52°F ![]()
[11.1°C]
Figure 46
An alternative method of controlling chillers in series involves staggering the set points of the two chillers. This results in the downstream chiller operating first and being preferentially loaded. Any portion of the load that the downstream chiller cannot meet is handled by the upstream chiller.
The example in Figure 46 shows the system operating at about 80 percent of design cooling load. As we mentioned earlier, with
40 |