Chiller-Plant Control
notes
Soft Loading
| 80°F |
|
|
| [26.7°C] | soft loading |
|
temperature |
|
| |
| (onechiller) |
| |
60°F |
|
| |
[15.6°C] |
|
| |
|
| ||
| set point |
| |
40°F | twochillers |
| |
| [4.4°C] |
| |
| 0 | 30 | 60 |
operatingtime, minutes | Figure 102 |
Another control function that is desirable is called soft loading. It is typically used when the system has been off for an extended period of time and the
Soft loading either delays turning on additional chillers or varies the chilled- water set point, allowing the operating chillers to gradually catch up to the building