Section 2 — Installation
Centurion
When using
NOTE:
Damage will result if the battery connections are made in reverse.
2.11 PREPARATION BEFORE START-UP
The instructions in this section assume that the standby generator has been properly installed, serviced, tested, adjusted and otherwise prepared for use by a competent, qualified installation contractor. Be sure to read the “Safety Rules” on Pages 2 and 3, as well as all other safety information in this manual, before attempting to operate this (and related) equipment.
2.11.1 PRIOR TO INITIAL START-UP
2.11.3 FUEL SYSTEM
Make sure the fuel supply system to the generator (a) delivers the correct fuel at the correct pressure and
(b)is properly purged and leak tested according to code. No fuel leakage is permitted. See Section 1.10, “Specifications” for more information.
2.11.4 GENERATOR SET LUBRICATION
Check the engine crankcase oil level before operating and, if necessary, add oil to the proper level – the dipstick “FULL” mark. Never operate the engine with the oil level below the dipstick “ADD” mark. See Section 1.10, “Specifications” and Section 1.14, “Engine Oil Recommendations”.
NOTE:
This engine is shipped from the manufacturer with
2.11.5 ENGINE COOLANT
Have the engine cooling system properly filled with the recommended coolant mixture. Check the system for leaks and other problems. See Section 1.10, “Specifications” and “Recommended Coolant”.
Prior to initially starting the generator, it must
!be properly prepared for use. Any attempt to crank or start the engine before it has been properly serviced with the recommended types and quantities of engine fluids (oil, coolant, fuel, etc.) may result in an engine failure.
Before starting the generator for the first time, the installer must complete the following procedures. For
2.11.2 TRANSFER SWITCH
If this generator is used to supply power to any electrical system normally powered by an electric utility, the National Electrical Code requires that a transfer switch be installed. The transfer switch prevents electrical backfeed between two different electrical systems. (For additional information, see the applicable transfer switch manual for this unit.)
The transfer switch, as well as the generator and other standby components, must be properly located and mounted in strict compliance with applicable codes, standards and regulations.
2.11.6 BELT TENSION
Check the engine fan belt tension and condition prior to placing the unit into service and at recommended intervals. Belt tension is correct when a force of approximately 22 pounds (10 kg), applied midway between pulleys, deflects the belt about 3/8- to 5/8- inch (10 to 16 mm).
2.11.7 ELECTRICAL SYSTEM
Make sure the generator is properly connected to an approved earth ground and/or ground rod.
Make sure the generator battery is fully charged, properly installed and interconnected, and ready for use.
Check to ensure that there are no loose electrical connections. Restrain any loose wires to keep them clear of any moving generator set components.