When using maintenance-free batteries, it is not necessary to check the specific gravity or electrolyte level. Have these procedures performed at the intervals specified in Section 4, “Maintenance.” A negative ground system is used. Battery connections are shown on the wiring diagrams. Make sure all batteries are correctly connected and terminals are tight. Observe battery polarity when connecting batteries to the generator set.

NOTE:

Damage will result if the battery connections are made in reverse.

2.11 PREPARATION BEFORE START-UP

The instructions in this section assume that the standby generator has been properly installed, serviced, tested, adjusted and otherwise prepared for use by a competent, qualified installation contractor. Be sure to read the “Safety Rules” on Pages 2 and 3, as well as all other safety information in this manual, before attempting to operate this (and related) equipment.

‹ 2.11.1 PRIOR TO INITIAL START-UP

‹2.11.3 FUEL SYSTEM

Make sure the fuel supply system to the generator (a) delivers the correct fuel at the correct pressure and

(b)is properly purged and leak tested according to code. No fuel leakage is permitted. See Section 1.10, “Specifications” for more information.

‹2.11.4 GENERATOR SET LUBRICATION

Check the engine crankcase oil level before operating and, if necessary, add oil to the proper level – the dipstick “FULL” mark. Never operate the engine with the oil level below the dipstick “ADD” mark. See Section 1.10, “Specifications” and Section 1.14, “Engine Oil Recommendations”.

NOTE:

This engine is shipped from the manufacturer with 15W-40 oil. This oil should be changed after 30 hours of operation.

‹2.11.5 ENGINE COOLANT

Have the engine cooling system properly filled with the recommended coolant mixture. Check the system for leaks and other problems. See Section 1.10, “Specifications” and “Recommended Coolant”.

Prior to initially starting the generator, it must

!be properly prepared for use. Any attempt to crank or start the engine before it has been properly serviced with the recommended types and quantities of engine fluids (oil, coolant, fuel, etc.) may result in an engine failure.

Before starting the generator for the first time, the installer must complete the following procedures. For follow-up maintenance information and/or service intervals, please refer to Section 4, “Maintenance.”

‹2.11.2 TRANSFER SWITCH

If this generator is used to supply power to any electrical system normally powered by an electric utility, the National Electrical Code requires that a transfer switch be installed. The transfer switch prevents electrical backfeed between two different electrical systems. (For additional information, see the applicable transfer switch manual for this unit.)

The transfer switch, as well as the generator and other standby components, must be properly located and mounted in strict compliance with applicable codes, standards and regulations.

‹2.11.6 BELT TENSION

Check the engine fan belt tension and condition prior to placing the unit into service and at recommended intervals. Belt tension is correct when a force of approximately 22 pounds (10 kg), applied midway between pulleys, deflects the belt about 3/8- to 5/8- inch (10 to 16 mm).

‹2.11.7 ELECTRICAL SYSTEM

Make sure the generator is properly connected to an approved earth ground and/or ground rod.

Make sure the generator battery is fully charged, properly installed and interconnected, and ready for use.

Check to ensure that there are no loose electrical connections. Restrain any loose wires to keep them clear of any moving generator set components.

12 Generac® Power Systems, Inc.

Image 14
Contents Centurion ‹ HOW to Obtain Service Authorized Service Dealer Location‹ Operation and Maintenance IntroductionInside Front Cover General Hazards Electrical Hazards Automatic System Operation Transfer SwitchGenerator Generator AC Connection SystemsMain Circuit Breaker ‹ 1.7.1 LOW OIL Pressure Switch‹ 1.7.2 High Coolant Temperature Switch Generator Fuel SystemUnpacking Lifting the GeneratorFuel Consumption SpecificationsReconfiguring the Fuel System ‹ 1.10.1 GeneratorGenerator Installation Torque SpecificationsBefore Installation Engine OIL RecommendationsBasic Standby Electric System Generator LocationGenerator Mounting Support ‹ 2.1.1 Nfpa StandardsGrounding the Generator Total Circuit Isolation MethodEmergency Circuit Isolation Method Generator AC Neutral Connections Transfer Switch Start Signal ConnectionsBattery Installation ‹ 2.10.1 Vented BatteriesPreparation Before START-UP ‹ 3.2.3 Fault Indicator Lamp Using a Standard GTS Transfer Switch‹ 3.2.2 AUTO/OFF/MANUAL Switch Control Console ComponentsWeekly Exercise Cycle ‹ 3.2.6 SET Exercise Time SwitchManual Transfer START-UP Automatic Operation Engine Block HeaterChecking Fluid Levels Cooling SystemOverload Protection for Engine DC Electrical System ‹ 4.5.4 Inspect Cooling System ‹ 4.4.2 Battery Fluid‹ 4.5.2 Check Battery ‹ 4.5.5 Perform Visual Inspection‹ 4.6.1 Cleaning the Generator Miscellaneous Maintenance‹ 4.5.10 Changing the Engine AIR Cleaner ‹ 4.5.11 Spark Plugs‹ 4.6.4 Battery Replacement ‹ 4.6.2 Battery‹ 4.6.3 Battery Maintenance ‹ 4.6.5 Rodent Protection‹ 4.7.2 Return to Service OUT of Service Procedure‹ 4.7.1 Removal from Service Fuel Pipe SizingScheduled Maintenance Service Maintenance Interval InformationLevel Maintenance Level Troubleshooting Points Problem Cause CorrectionCenturion Liquid-cooled 15 kW and 25 kW Generators Installation Diagram Section DC-VR Customer Connection 120/240V 1-PHASE To Control Panel Terminal Strip Cover Connector Housing Housing Governor ConnectorConnector Interface Assembly ASM Motor StepperDampener Vibration BASE,MOUNTING 1.5L STNRD&ACSTCWasher Shakeproof EXT 5/16 STL Washer Flat 5/16 ZincWeld Stud Under Roof Assembly Cover Access Assembly BASE-DOOR Ground WireGRD Wire Assy 99HSB Roof ACSTC&STND Cmprtmnt 1.5LPanel for Access Cover Cable Washer Self Locking Dome Roof Acstc & Stnd Cmprtmnt 1.5LDoor Weldment 1.5 EPS Baffle Cntrl PNL 1.5L AcousticTo a Hourmeter Wire AssemblySilksc Holder FuseHardware Ground Wire Starter Switch OIL PressureARM Adjust Alternator ENGINE-1.5L16 7 Venturi 1.5L Modine Tank Coolant RecoveryRadiator 1.5L Guard FAN 1.5L ModineVapor Weldment Mounting Base Cover AIR CleanerGasket AIR Cleaner Adapter Flange Fuel InletTo Engine Crankshaft Assy Rotor 15KW Housing BlowerAssy Rotor 10KW Assy Rotor 20KWBRACKET, Battery Hold Down ASSY,WIRE#16 REDBOOT, Battery Cable Battery Post Cover RED+Saddle 2 Inch Manifold Exhaust 1.5LNipple TOE 1.5NPTX5.5 BLK Iron PIPE,EXHAUST 1.5L STNDRD&ACSTCPURCHASER’S/OWNER’S Warranty Responsibilities Your Warranty Rights and ObligationsMANUFACTURER’S Emission Control System Warranty Coverage Emission Control System Warranty Emission Related Parts Include the FollowingWarranty Schedule