7.Normal no load frequency is 62.0 to 62.5 Hz. If adjustment is needed at no load, slowly rotate the governor adjustment nut (Figure 14) clockwise and/or counterclockwise until frequency is 62.0 to 62.5 Hz.

AUTOMATIC OPERATION SEQUENCE

Figure 14 — Governor Adjustment Nut

Governor

Adjustment Nut

8.Turn the service disconnect to the transfer switch off. The transfer switch will connect to the generator after a short time delay.

9.Load generator to rated Natural Gas rating.

10.Connect an accurate frequency meter to the load side of the main circuit breaker (on the back of the control panel). Frequency should be above 57.0 Hz.

11.If frequency is below 57.0 Hz, slowly rotate the governor adjustment nut clockwise and/or counterclockwise until frequency is above 57.0 Hz.

12.Turn the service disconnect to the transfer switch on. The transfer switch will connect to the utility after a short time delay.

13.Set the AUTO/OFF/MANUAL switch to OFF.

14.After the engine has stopped running, reinstall the control panel wiring cover to the air intake guard.

15.Reinstall the air intake and control panel access doors.

16.Set the AUTO/OFF/MANUAL switch to AUTO.

The generator’s control panel houses a logic control circuit board.This control board constantly monitors utility power source voltage. Should that voltage drop below a preset level, control board action will signal the engine to crank and start.

When utility source voltage is restored above a preset voltage level, the engine is signaled to shut down.

The actual system operation is not adjustable and is sequenced by sensors and timers on the control board, as follows:

Utility Voltage Dropout Sensor

This sensor monitors utility source voltage.

If utility source voltage drops below about 70 percent of the nominal supply voltage, the sensor energizes a

6-second timer.The timer is used to ‘sense’ brown-outs.

Once the timer has expired, the engine will crank and start.

Utility Voltage Pickup Sensor

This sensor monitors utility power supply voltage.When that voltage is restored above 80 percent of the nominal source voltage, a time delay starts timing and the engine will go to engine cool-down.

Engine Cool-down Timer

When the load is transferred back to the utility power source, the engine cool-down timer starts timing.

The timer will run for about one minute, then the generator will stop.

Minimum engine run time is 5 minutes.

15

Image 15
Contents 10kW / 12kW Rated Customer Responsibilities Table of ContentsInstaller Responsibilities Equipment DescriptionAmp fuse Before working on the equipment Important Safety RulesHazard Symbols and Meanings Rotating Parts Electrical ShockInstallation Procedures Area Fuel and Electrical Inlet DimensionsLifting the Generator Conduit AttachmentDoor Access DoorsBattery InsertInstallation Manual To Remove an Access Door To Install an Access DoorGaseous Fuel System To Home Standby From FuelLoad Fuel ConsumptionFuel Pipe Sizing 10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ftVolt DC, .5 Amp Output Internal power supply Know Your System Control BoardRemote LED Output Grounding the Generator Fault Detection SystemTo install the remote LED panel Generator AC Connection SystemEngine Oil Battery ConnectionBefore Initial START-UP System Control PanelFuel System Selection Servicing the BatteryTo configure the fuel system for LP use Do not dispose of battery in a fireEngine Adjustment Install the 15 Amp fuse in the control panelInitial START-UP no Load Utility Voltage Dropout Sensor Engine Cool-down TimerAdjustment Nut Automatic Operation SequenceSetting Exercise Timer Installation InspectionTo perform the Set Exercise procedure Fuel Comparison Chart Physical Properties Butane Propane Natural GasWithdrawal Rate 32F 20F 10F 30F 40F Responsabilidades DEL Instalador Tabla DE ContenidoDescripción DEL Equipo Responsabilidades DEL ClienteExplosión PrecauciónAdvertencia Símbolos de Peligro y SignificadosProcedimientos DE Instalación 13.5 Dimensiones de la Entrada para Electricidad y CombustibleElevación del Generador NPTEntrada de Combustible Puertas de AccesoPara Para Retirar una Puerta de AccesoPara Instalar una Puerta de Acceso Sistema DE Combustible Gaseoso AdvertenciaFigura 19 Manómetro Instalado Transitoriamente Gas Natural peso específico = Dimensiones de la Cañería de CombustibleConsumo de Combustible Modelo Gas Natural Vapor de PLConozca LA Tarjeta DE Control DE SU Sistema Sistema de Detección de Fallas Sistema de Conexión de c.a. del GeneradorConexión a Tierra del Generador Interconexiones del Circuito de ControlConexión de la Batería Antes DEL Arranque Inicial DEL MotorPanel de Control del Sistema Aceite de MotorSistema de Suministro de Combustible Para configurar el sistema de combustible para uso de LPPeligro Selección DEL Sistema DE CombustibleArranque Inicial SIN Carga Instale el fusible de 15 Amperios en el panel de controlFije el interruptor AUTO/OFF/MANUAL en la posición Ajuste del Motor Del ReguladorCargue el generador al valor nominal de gas natural Configuración DEL Temporizador DE Práctica Secuencia DE Operación AutomáticaInspección Posterior a LA Instalación Cuadro de Comparación de Combustibles Propiedades físicas Butano Propano Gas naturalTasa de consumo 32F 20F 10F 30F 40F Description DE Léquipement Responsabilités DE LinstallateurGuide dInstallation Table DES MatièresSymboles de Danger et Moyens AvertissementExplosion Feu Procédures Dinstallation Directives Générales Concernant lEmplacement Soulèvement de la GénératriceConnecteur de tuyauterie De combustible Pour enlever une porte daccès Tuyau ici Tuyau fourni par linstallateurPortes dAccès PourLE Système DE Combustible Gazeux Avertissement Pour installer une porte daccèsIl faudrait inclure une sortie pour manomètre Le groupe électrogène a été réglé en usine pourGaz Naturel densité = 0,65 Consommation de CombustibleGrosseur du Tuyau de Combustible Modèle Gas Naturel Vapeur PLSortie de panneau DEL à distance Mise à la Masse de la Génératrice Interconnexions du Circuit de CommandeTableau de Commande du Système Système de Branchement C.A. de la GénératriceAvant LE Démarrage Initial DU Moteur Huile à MoteurBranchement de la Batterie Entretien de la Batterie Sélection DU Système DE CombustibleSystème dAlimentation en Combustible Réglez linterrupteur AUTO/OFF/MANUAL sur AutoDu Régulateur Démarrage Initial SansRéglage du Moteur Réglez linterrupteur AUTO/OFF/MANUAL sur ManualVérification Installation Séquence DE Fonctionnement AutomatiqueRéglage DE LA Minuterie DE Cycle Dexercice Poids† Indice d’octane Recherche Charte de Comparaison des CombustiblesPropriétés physiques Butane Propane Gaz naturel Densité 31,26