Installation Manual

INSTALLATION PROCEDURES

Required Specialty Tools/Equipment

Two 48” lengths of 1” OD pipe (NOT conduit)

Hole punches for 16ga steel

Torque screwdriver, 5 to 50 inch-pound range

Unpacking Precautions

The unit is shipped bolted to its mounting pad, ready for installation. Avoid damage from dropping, bumping, collision, etc. Store and unpack carton with the proper side up, as noted on the shipping carton.

CAUTION

Installing the 15A fuse could cause the engine to start.

Observe that the 15 Amp fuse has been removed from the control panel for shipping.

DO NOT install this fuse until all plumbing and wiring has been completed and inspected.

Delivery Inspection

After removing the carton, carefully inspect the Home Standby Generator for any damage that may have occurred during shipment.

IMPORTANT: If loss or damage is noted at time of delivery, have the person(s) making delivery note all damage on the freight bill and affix his signature under the consignor's memo of loss or damage. If loss or damage is noted after delivery, separate the damaged materials and contact the carrier for claim procedures. Missing or damaged parts are not warranted.

Shipment Contents

The Home Standby Generator is supplied with:

Home Standby Generator

Pre-attached mounting pad

One 24” flexible hook-up hose

Installation and start-up manual (P/N 192385GS)

Operator’s manual(P/N 192384GS)

Illustrated parts list manual (P/N 193208GS for model 01815 or P/N 193918GS for model 01938)

Installation checklist (P/N 190840GS)

Three access door keys

Four lifting hole plugs

Oil fill spout

Touch-up paint

One spare 15A fuse

Diagnostic LED kit (diode/plate/decal/pin connectors (2))

Home Standby Generator Location

Before installing generator, consult with homeowner and convey the following guidelines which may affect the desired location.

Generator Clearances

WARNING

Exhaust heat/gases can ignite combustibles or structures causing a fire.

Keep at least 5 ft. (152 cm) clearance on all sides of generator including overhead.

Place generator in a well ventilated area, which will allow for removal of deadly exhaust gas. DO NOT install generator where exhaust gas could accumulate and enter inside or be drawn into a potentially occupied building. Ensure exhaust gas is kept away from any windows, doors, ventilation intakes or other openings that can allow exhaust gas to collect in a confined area (Figure 1). Prevailing winds and air currents should be taken into consideration when positioning generator.

Using a generator indoors WILL KILL YOU IN MINUTES.

Exhaust contains carbon monoxide, a poison gas you cannot see or smell.

NEVER use in the home ONLY use outdoors and

or in partly enclosed far from open windows, areas such as garages. doors, and vents.

General Location Guidelines

Install the unit outdoors ONLY.

Place the unit in a prepared location that is flat and has provisions for water drainage.

Install the unit in a location where sump pump discharge, rain gutter down spouts, roof run-off, landscape irrigation, or water sprinklers will not flood the unit or spray the enclosure and enter any air inlet or outlet openings.

4

Image 4
Contents 10kW / 12kW Rated Table of Contents Installer ResponsibilitiesEquipment Description Customer ResponsibilitiesImportant Safety Rules Hazard Symbols and MeaningsRotating Parts Electrical Shock Amp fuse Before working on the equipmentInstallation Procedures Fuel and Electrical Inlet Dimensions Lifting the GeneratorConduit Attachment AreaAccess Doors BatteryInsert DoorTo Install an Access Door Installation Manual To Remove an Access DoorGaseous Fuel System From Fuel To Home StandbyFuel Consumption Fuel Pipe Sizing10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ft LoadKnow Your System Control Board Volt DC, .5 Amp Output Internal power supplyRemote LED Output Fault Detection System To install the remote LED panelGenerator AC Connection System Grounding the GeneratorBattery Connection Before Initial START-UPSystem Control Panel Engine OilServicing the Battery To configure the fuel system for LP useDo not dispose of battery in a fire Fuel System SelectionInstall the 15 Amp fuse in the control panel Engine AdjustmentInitial START-UP no Load Engine Cool-down Timer Adjustment NutAutomatic Operation Sequence Utility Voltage Dropout SensorInstallation Inspection Setting Exercise TimerTo perform the Set Exercise procedure Physical Properties Butane Propane Natural Gas Fuel Comparison ChartWithdrawal Rate 32F 20F 10F 30F 40F Tabla DE Contenido Descripción DEL EquipoResponsabilidades DEL Cliente Responsabilidades DEL InstaladorPrecaución AdvertenciaSímbolos de Peligro y Significados ExplosiónProcedimientos DE Instalación Dimensiones de la Entrada para Electricidad y Combustible Elevación del GeneradorNPT 13.5Puertas de Acceso ParaPara Retirar una Puerta de Acceso Entrada de CombustibleSistema DE Combustible Gaseoso Advertencia Para Instalar una Puerta de AccesoFigura 19 Manómetro Instalado Transitoriamente Dimensiones de la Cañería de Combustible Consumo de CombustibleModelo Gas Natural Vapor de PL Gas Natural peso específico =Conozca LA Tarjeta DE Control DE SU Sistema Sistema de Conexión de c.a. del Generador Conexión a Tierra del GeneradorInterconexiones del Circuito de Control Sistema de Detección de FallasAntes DEL Arranque Inicial DEL Motor Panel de Control del SistemaAceite de Motor Conexión de la BateríaPara configurar el sistema de combustible para uso de LP PeligroSelección DEL Sistema DE Combustible Sistema de Suministro de CombustibleInstale el fusible de 15 Amperios en el panel de control Arranque Inicial SIN CargaFije el interruptor AUTO/OFF/MANUAL en la posición Del Regulador Ajuste del MotorCargue el generador al valor nominal de gas natural Secuencia DE Operación Automática Configuración DEL Temporizador DE PrácticaInspección Posterior a LA Instalación Propiedades físicas Butano Propano Gas natural Cuadro de Comparación de CombustiblesTasa de consumo 32F 20F 10F 30F 40F Responsabilités DE Linstallateur Guide dInstallationTable DES Matières Description DE LéquipementAvertissement Symboles de Danger et MoyensExplosion Feu Procédures Dinstallation Soulèvement de la Génératrice Directives Générales Concernant lEmplacementConnecteur de tuyauterie De combustible Tuyau ici Tuyau fourni par linstallateur Portes dAccèsPour Pour enlever une porte daccèsPour installer une porte daccès LE Système DE Combustible Gazeux AvertissementLe groupe électrogène a été réglé en usine pour Il faudrait inclure une sortie pour manomètreConsommation de Combustible Grosseur du Tuyau de CombustibleModèle Gas Naturel Vapeur PL Gaz Naturel densité = 0,65Sortie de panneau DEL à distance Interconnexions du Circuit de Commande Tableau de Commande du SystèmeSystème de Branchement C.A. de la Génératrice Mise à la Masse de la GénératriceHuile à Moteur Avant LE Démarrage Initial DU MoteurBranchement de la Batterie Sélection DU Système DE Combustible Système dAlimentation en CombustibleRéglez linterrupteur AUTO/OFF/MANUAL sur Auto Entretien de la BatterieDémarrage Initial Sans Réglage du MoteurRéglez linterrupteur AUTO/OFF/MANUAL sur Manual Du RégulateurSéquence DE Fonctionnement Automatique Vérification InstallationRéglage DE LA Minuterie DE Cycle Dexercice Charte de Comparaison des Combustibles Propriétés physiques Butane Propane Gaz naturelDensité 31,26 Poids† Indice d’octane Recherche