Piping must be of the correct size to maintain the required supply pressures and volume flow under varying generator load conditions with all gas appliances connected to the fuel system turned on and operating.

Use an approved pipe sealant or joint compound on all threaded fittings to reduce the possibility of leakage.

Installed piping must be properly purged and leak tested, in accordance with applicable codes and standards.

WARNING

Propane and Natural Gas is extremely flammable and explosive.

Fire or explosion can cause severe burns or death.

Before placing the Home Standby Generator into service, the fuel system lines must be properly purged and leak tested.

NO leakage is permitted.

Consider the following factors when planning to install the fuel supply system:

The Home Standby Generator engine is fitted with a fuel mixer system that meets the specifications of the California Air Resources Board for “tamper-proof” dual fuel systems. The unit will run on natural gas or liquefied propane.

A minimum of one accessible, approved manual shutoff valve shall be installed in the fuel supply line within 6 ft (1.8 m) of the Home Standby Generator. A union or flanged connection shall be provided downstream from this valve to permit removal of controls.

Natural gas fuel supply pressure at the generator's fuel inlet port should be between 5 to 7 inches of water (in. W.C.) at full load. LP fuel supply pressure should be 11 to 14 inches of water (in.W.C.) at full load.

The Home Standby Generator unit has been

factory set to run on natural gas. If you need to change from natural gas to LP gas, the unit will need to be reconfigured, as described on page 13.

It is recommended that the fuel connection incorporate the following components:

A manual fuel shut-off valve located in the interior of the building.

A manual fuel shut-off valve located outside the building, just before the generator unit.

Where the formation of hydrates or ice is known to occur, piping should be protected against freezing.The termination of hard piping should include a sediment trap where condensate is not likely to freeze.

A manometer port should be provided.

The manometer port permits temporary installation of a manometer (Figure 5), to ensure that the engine receives the correct fuel pressure to operate efficiently throughout its operating range.

Figure 5 — Temporary Manometer Installed

NOTE: A digital manometer, P/N 19495, is available at your local Briggs & Stratton service center.

When the initial test runs are completed, the manometer is removed and the port is plugged. A typical final fuel connection assembly is shown in Figure 6.

Figure 6 — Completed Fuel Connections

From Fuel

Supply Line

To Home Standby

Generator

8

Image 8
Contents 10kW / 12kW Rated Table of Contents Installer ResponsibilitiesEquipment Description Customer ResponsibilitiesImportant Safety Rules Hazard Symbols and MeaningsRotating Parts Electrical Shock Amp fuse Before working on the equipmentInstallation Procedures Fuel and Electrical Inlet Dimensions Lifting the Generator Conduit Attachment AreaAccess Doors BatteryInsert DoorGaseous Fuel System Installation Manual To Remove an Access DoorTo Install an Access Door From Fuel To Home StandbyFuel Consumption Fuel Pipe Sizing10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ft LoadRemote LED Output Volt DC, .5 Amp Output Internal power supplyKnow Your System Control Board Fault Detection System To install the remote LED panelGenerator AC Connection System Grounding the GeneratorBattery Connection Before Initial START-UPSystem Control Panel Engine OilServicing the Battery To configure the fuel system for LP useDo not dispose of battery in a fire Fuel System SelectionInitial START-UP no Load Engine AdjustmentInstall the 15 Amp fuse in the control panel Engine Cool-down Timer Adjustment NutAutomatic Operation Sequence Utility Voltage Dropout SensorTo perform the Set Exercise procedure Setting Exercise TimerInstallation Inspection Withdrawal Rate 32F 20F 10F 30F 40F Fuel Comparison ChartPhysical Properties Butane Propane Natural Gas Tabla DE Contenido Descripción DEL EquipoResponsabilidades DEL Cliente Responsabilidades DEL InstaladorPrecaución AdvertenciaSímbolos de Peligro y Significados ExplosiónProcedimientos DE Instalación Dimensiones de la Entrada para Electricidad y Combustible Elevación del GeneradorNPT 13.5Puertas de Acceso ParaPara Retirar una Puerta de Acceso Entrada de CombustibleSistema DE Combustible Gaseoso Advertencia Para Instalar una Puerta de AccesoFigura 19 Manómetro Instalado Transitoriamente Dimensiones de la Cañería de Combustible Consumo de CombustibleModelo Gas Natural Vapor de PL Gas Natural peso específico =Conozca LA Tarjeta DE Control DE SU Sistema Sistema de Conexión de c.a. del Generador Conexión a Tierra del GeneradorInterconexiones del Circuito de Control Sistema de Detección de FallasAntes DEL Arranque Inicial DEL Motor Panel de Control del SistemaAceite de Motor Conexión de la BateríaPara configurar el sistema de combustible para uso de LP PeligroSelección DEL Sistema DE Combustible Sistema de Suministro de CombustibleFije el interruptor AUTO/OFF/MANUAL en la posición Arranque Inicial SIN CargaInstale el fusible de 15 Amperios en el panel de control Cargue el generador al valor nominal de gas natural Ajuste del MotorDel Regulador Inspección Posterior a LA Instalación Configuración DEL Temporizador DE PrácticaSecuencia DE Operación Automática Tasa de consumo 32F 20F 10F 30F 40F Cuadro de Comparación de CombustiblesPropiedades físicas Butano Propano Gas natural Responsabilités DE Linstallateur Guide dInstallationTable DES Matières Description DE LéquipementExplosion Feu Symboles de Danger et MoyensAvertissement Procédures Dinstallation Connecteur de tuyauterie De combustible Directives Générales Concernant lEmplacementSoulèvement de la Génératrice Tuyau ici Tuyau fourni par linstallateur Portes dAccèsPour Pour enlever une porte daccèsPour installer une porte daccès LE Système DE Combustible Gazeux AvertissementLe groupe électrogène a été réglé en usine pour Il faudrait inclure une sortie pour manomètreConsommation de Combustible Grosseur du Tuyau de CombustibleModèle Gas Naturel Vapeur PL Gaz Naturel densité = 0,65Sortie de panneau DEL à distance Interconnexions du Circuit de Commande Tableau de Commande du SystèmeSystème de Branchement C.A. de la Génératrice Mise à la Masse de la GénératriceBranchement de la Batterie Avant LE Démarrage Initial DU MoteurHuile à Moteur Sélection DU Système DE Combustible Système dAlimentation en CombustibleRéglez linterrupteur AUTO/OFF/MANUAL sur Auto Entretien de la BatterieDémarrage Initial Sans Réglage du MoteurRéglez linterrupteur AUTO/OFF/MANUAL sur Manual Du RégulateurRéglage DE LA Minuterie DE Cycle Dexercice Vérification InstallationSéquence DE Fonctionnement Automatique Charte de Comparaison des Combustibles Propriétés physiques Butane Propane Gaz naturelDensité 31,26 Poids† Indice d’octane Recherche
Related manuals
Manual 48 pages 28.98 Kb