Towing Instructions See Figure 4-1for component identification.

1.Be sure the generator is off.

2.Shut all enclosure doors and latch the locks.

3.Back the tow vehicle to within a few inches of the trailer coupler (Pintle or Ball).

4.Be sure the Coupler Handle is in the “UP” (open) position or the Pintle Hook is Open.

5.Adjust the trailer jack for the height of the hitch on the tow vehicle.

6.Back the tow vehicle so the trailer coupler is directly over the tow vehicle ball hitch or the Pintle hook.

7.Lower the trailer so the trailer coupler rests securely on the ball hitch of the tow vehicle. Move the Coupler Handle to the horizontal position and lock it in place to securely hold the ball hitch of the tow vehicle.

OR

Latch the Pintle and lock the Pintle device securely.

Note: If this is not done properly, the trailer may become unhitched when it is towed.

8.Retract the front jack, pull the jack pin and rotate the jack 90 degrees from vertical to the horizontal position, making sure the self−locking pin reseats and the jack is secured to the tow bar (stowed position).

9.Connect safety chains, making sure to cross them. If a safety chain is too long, simply twist it a few turns to shorten the chain before attaching to the tow vehicle.

10.Connect the trailer light connector to the tow vehicle.

11.Test the trailer lights to ensure they are operational.

12.Check tires for proper inflation.

13.Check wheel lug nuts for correct tightness (see Lug Nut Tightness).

Wheel nuts/bolts should be torqued before the first road use and after each wheel removal. Check and re−torque after the first 50 miles and again at 100 miles. Check periodically thereafter.

14.Verify that all jacks, pins, cables, and doors are secured and trailer tongue is level.

15.Remove tire chocks (if used). These prevent the trailer from moving when parked.

Lug Nut Tightness Be sure to use only the fasteners matched to the cone angle of your wheel (usually 60 or 90 degrees.) The proper procedure for attaching your wheel is as follows, see Figure 4-2:

1.If a wheel is removed and installed, start each nut by hand to prevent cross threading.

2.Tighten lug nuts in the following sequence.

a.Tighten each bolt in the sequence shown in Figure 4-2and tighten to one half the torque specified until all lug nuts are tightened to one half the torque.

b.Tighten each bolt in the sequence shown in Figure 4-2and tighten to three fourths the torque specified until all lug nuts are tightened to three fourths the torque.

c.Tighten each bolt in the sequence shown in Figure 4-2and tighten each to the specified torque until all lug nuts are tightened to the correct torque.

Figure 4-2 Lug Nut Tightening Specifications

Tightening Sequence

Torque Specification

1

 

1

 

1

1

 

10

1

8

 

 

 

 

 

8

6

 

 

4

3

3

 

6

 

3

 

6

4

 

 

4

 

 

3

 

 

 

 

3

 

4

 

 

 

5

 

4

 

5

 

 

 

 

 

 

 

 

 

 

2

5

 

 

5

7

7

 

9

2

 

2

2

 

2

 

 

 

 

 

 

4 Bolt

 

5 Bolt

 

6 Bolt

8 Bolt

 

 

10 Bolt

 

Description

Application

 

Minimum Torque (ft−lbs.)

 

Maximum Torque (ft−lbs.)

1/2” Cone nut

12” − 13” Wheel

 

 

50

 

65

 

 

 

14” − 16” Wheel

 

 

90

 

120

 

 

5/8” Cone nut

Flat Disc Wheel

 

 

175

 

225

 

 

5/8” Cone nut

Clamp Ring

 

 

190

 

210

 

 

3/4” Hex nut

Demountable Ring Clamp

210

 

260

 

 

4-4 Operation

MN2417

Image 26
Contents Tier 2/3 Towable Generators Trailer and Skid Mounted California Proposition 65 Warning Table of Contents Ii Table of Contents MN2417 Section Product Safety Information Read This Manual ThoroughlyOperation Statements Precaution Statements Used In This ManualProperty On next MN2417 Product Safety Information Operation Statements Burn Statements Installation Statements Installation Statements Maintenance Statements Product Safety Information MN2417 Limited Warranty Labor PartsGeneral Information MN2417 Section Receiving & Installation Generator Mounting Skid Fuel Connections InstallationHot Exhaust Gasses Protection Standby Power RatingsPrime Power Ratings Single Phase Connections Receptacle Panel Single PhaseBattery Charger Considerations Three Phase ConnectionsTransfer Switch Considerations General Wiring ConsiderationsFrame Ground Connection Battery Installation Post Installation Checks Recommended Engine Oil and Battery TypeOil & Battery Recommendations Post Installation Checks Tow Vehicle Tow Hitch Capacity Towing the Generator Selecting the Proper Towing Equipment Towing Heavy Trailer Loads Trailer Component Identification Lug Nut Tightening Specifications Page Three/Single Phase Operation Receptacle Panel Load Connections, see FigureVoltage Reconnect and Adjustment Operator Control Panel ComponentsAuto Start Procedure Manual Start ProcedureManual Stop Procedure Alarm & Warning Conditions Digital Engine Controller Description EM0046A21 MRS17AUT Mode OFF ModeMAN Mode Measurement MenuECU Alarm List Adjustment MenuAlarm List Possible Warnings Sensor fail FLS see TableShut down SD see Table Binary outputs Inputs and OutputsBinary Inputs Analog Inputs Set points Basic SetpointsStabil Time 10 Engine Setpoints10Engine Setpoints 11 Engine Protect Setpoints12 Generator Protect Setpoints 13 Sensor Spec Setpoints 14 IOM/PTM Module Setpoints+ D+ Jdic General EngineProblems and Solutions Troubleshooting Guide1Troubleshooting Guide Load too large for unitTroubleshooting and Maintenance MN2417 Appendix a Wiring Diagrams Part numberFigure A-1 TS25 Connection Diagram Figure A-2 TS25 Connection Diagram Figure A-3 TS25 Connection Diagram Figure A-4 TS25 Connection Diagram Figure A-5 TS25 Connection Diagram Figure A-6 TS25 Connection Diagram Figure A-7 TS35 Connection Diagram Figure A-8 TS35 Connection Diagram Figure A-9 TS35 Connection Diagram Figure A-10 TS35 Connection Diagram Figure A-11 TS35 Connection Diagram Figure A-12 TS35 Connection Diagram Figure A-13 TS35 Power Connection Diagram Figure A-14 TS60 Connection Diagram Figure A-15 TS60 Connection Diagram Figure A-16 TS60 Connection Diagram Figure A-17 TS60 Connection Diagram Figure A-18 TS60 Connection Diagram Figure A-19 TS60 Connection Diagram Figure A-20 TS60 Connection Diagram Figure A-21 TS80 Connection Diagram Figure A-22 TS80 Connection Diagram Figure A-23 TS80 Connection Diagram Figure A-24 TS80 Connection Diagram Figure A-25 TS80 Connection Diagram Figure A-26 TS80 Connection Diagram Figure A-27 TS80 Connection Diagram Figure A-28 TS80 Connection Diagram Figure A-29 TS80 Connection Diagram Figure A-30 TS80 Connection Diagram Figure A-31 TS400 Connection Diagram Figure A-32 TS400 Connection Diagram Figure A-33 TS400 Connection Diagram Figure A-34 TS400 Connection Diagram Figure A-35 TS400 Connection Diagram Figure A-36 TS400 Connection Diagram Figure A-37 TS400 Connection Diagram Figure A-38 TS400 Connection Diagram Figure A-39 TS400 Connection Diagram Baldor District Offices Baldor Electric Company