Equipment Inspection and Startup
2.0EQUIPMENT INSPECTION AND STARTUP
2.1Internal Inspection
A detailed internal inspection should be performed after the unit is in place and before it is ener- gized, to ensure trouble free startup. The same internal inspection should be carried out when per- forming preventive maintenance.
! WARNING
Verify that all incoming line voltage (power) and
Open the unit - Gain access to the internal components of the Liebert FPC unit by removing the exterior panels and internal accent panels.
Visually inspect - Be sure wiring and components are not damaged.
Check power connections - Check all power connections for tightness. Refer to Tables 11 through 14 for torque requirements of all electrical connections.
Perform formal detailed inspection - Follow the procedures described in 3.0 - Inspection and
2.2Startup
Checklists
Follow the detailed
Initial System Startup
A qualified electrician must be employed to perform the equipment inspection and startup. Liebert system startup may be arranged by calling your local Liebert sales representative or Liebert Global Services. In the United States, call
Warranty
A copy of the appropriate checklist (furnished with the equipment) must be completed, signed, dated and returned to Liebert Corporation. Warranty coverage of the equipment is not effective unless the checklist has been received by the factory.
! WARNING
Equipment inspection and startup should be performed only by trained personnel. Hazardous voltages are present during startup procedures.
Electrical safety precautions must be followed throughout inspection and startup.