Emerson FPC user manual Unit Preparation, Location Considerations

Page 9

Installation Instructions

1.1.3Unit Preparation

The Liebert FPC may be easily removed from the shipping pallet and installed by customer person- nel. A typical procedure is as follows:

1.Set the palletized assembly in a level area where there is enough room to roll the Liebert FPC and entire cable assembly off the pallet onto the floor.

2.Cut the shipping bands.

! WARNING

The shipping bands may be under tension and may snap violently when cut. Use eye, face and hand protection to guard against injury when the bands are cut.

3.Remove the factory-provided ramp from its shipping position.

One ramp is provided for every five units. Ramps are packed either in front of or on top of a set of cable reel(s).

4.Place the ramp adjacent to the pallet to provide a smooth path from pallet to floor.

5.Remove side panels from the Liebert FPC, if supplied. An Allen wrench for the side panels is furnished in the installation packet.

6.Remove the bolts and two mounting brackets holding the unit to the shipping pallet. Mounting brackets are located on either side of the unit.

7.If cables are on wheeled cable reel(s), remove the bolts holding the reel(s) to the pallet and remove the nailed-on shipping blocks.

8.Roll the unit off the pallet onto the floor, carefully guiding the cable reel(s) after it.

9.Roll the FPC and the cable reel(s) to the installation area. For units to be placed on a raised floor, use care when positioning unit over the floor cutout to prevent the casters from falling through the cutout.

! CAUTION

Before maneuvering the unit into its final position, read and follow all advisories in 1.1.4 - Location Considerations.

1.1.4Location Considerations

The Liebert FPC should be placed near the load(s) it will supply, preferably within the data center.

Equipment location should employ the shortest output distribution cable runs consistent with logical equipment arrangement and allowance for expansion.

The FPC is intended for indoor installation in an area with ambient temperatures of 32°F to 104°F (0°C to 40°C) with a relative humidity of 0% to 95% (non-condensing).

Bottom clearance is required for units with bottom entry/exit of cables. This clearance may be pro- vided by a raised floor at least 6" (150mm) high. Figures 1 and 2 show the typical raised-floor cutout dimensions for cables and cooling airflow.

When units are not installed on a raised floor, or if the raised floor will not support the unit, optional floor pedestals may be used. (CSA regulations require FPC arrangements employing a raised floor. Non-raised floor applications are not CSA approved.) Units with top cable exit provisions do not require bottom clearance.

Recommended minimum service clearances are shown in Figure 3. The National Electrical Code (NEC) requires the indicated front and rear clearances for service access. Clearance above the unit is required for cooling airflow (exhaust). Units with optional distribution monitoring also require service access clearance on the left side.

As do all electrical devices, the Liebert FPC produces heat under normal operation. (See Table 3.) This heat must be accounted for when calculating the environmental conditions of the room.

5

Image 9
Contents Liebert FPC Page Table of Contents Figures Important Safety Instructions Unpacking and Installation Unpacking and Preliminary InspectionHandling Considerations Inch cabinet weight Cutout Dimensions cooling airflow Footprint and Floor cable accessFront FrontLocation Considerations Unit PreparationSee Notes 2 Front and rear access is required. See Notes 1 Liebert FPC heat outputFull Load Heat Output Unit kVA BTU/Hr kW Floor pedestal details Floor Pedestal InstallationPower and Control Wiring Additional Distribution Mounting & WiringInput Power Connections Liebert FDC Distribution MountingElectrical connection location for 23 584mm cabinet FPC15000 Rev FPC15002 Rev Suggested minimum input wire size data Main input circuit breaker interrupting rating Main input junction box electrical connections 4 wire Junction Box InstallationLow-voltage control junction box dimensions, typical Main input power junction box dimensions, typicalEquipment Grounding System GroundingGrounding Electrode Conductor for FPCs With Transformer Signal Reference GridMinimum grounding electrode conductor size AWG Output VoltageSystemTypical Liebert FPC without transformer grounding Typical Liebert FPC With transformer grounding arrangementOutput Power Connections Liebert FPC +24VDC Liebert FPCUnit EPO MainWiring Low Voltage Terminal StripFactory Optional Customer Alarm Inputs Summary Typical control wiring for units with monitoringWarranty ChecklistsInternal Inspection StartupPanelboard main circuit breaker torque specifications Torque specifications, generalBranch circuit breaker torque specifications Terminal block compression lug torque specificationsUnit Serial Number Unit Model Number Date InspectionStartup Monitoring System Check-Out Customer Alarms Normal System Shutdown Startup ProceduresNormal System Turn on Manual RestartAlarm Present/Silence Power Monitor PanelBasic Monitor Panel Units Without Monitoring FPC16000Operating Instructions Ascii interface default parameters RS-232 Ascii port customer commandsParameter Default Field # Data item Units Monitored parameters data definitionsInspection and Cleaning RepairInspection Schedule Page Iti Ne tTi n That