1.0INSTALLATION INSTRUCTIONS

1.1Unpacking and Installation

NOTE

Read the entire manual before installing and operating the system. Upon receipt of a Liebert FPC™, the installer should perform the following steps to ensure a quality installation.

1.1.1Unpacking and Preliminary Inspection

A quality installation begins on the receiving dock.

1.Inspect the shipping crate(s) for damage or signs of mishandling before unpacking the unit(s). Check the Shock-Watch™ indicator.

2.Remove the packing and inspect the equipment for any obvious shipping damages.

3.If the FPC was shipped in an export crate, open the shipping crate carefully.

Use care to avoid puncturing the container with sharp objects that would damage the contents.

4.Remove the packing and vapor barriers and inspect the equipment for any obvious shipping damages.

NOTE

The units should not be loosened from the shipping pallet until all handling by fork lift or pallet jack is completed. Complete internal inspection should be accomplished only after equipment positioning and prior to electrical hookup.

5.If any damage is observed, immediately file a damage claim with the shipping agency and forward a copy to:

Liebert Corporation

1050 Dearborn Drive P.O. Box 29186 Columbus, Ohio 43229 USA

1.1.2Handling Considerations

The Liebert FPC(and cables, if furnished) is bolted to a wooden pallet to allow handling by forklift equipment.

The Liebert FPC and cable reels are furnished with casters to allow the unit to be rolled into place after it has been unbolted from the pallet. The FPC should be kept on the shipping pallet until it has been moved by forklift as close as practical to its installation location.

Refer to the cabinet drawings furnished with the FPC for the unit’s size and weight. Typical cabinet dimensions and weights are shown in Figures 1 and 2.

The route to the FPC’s installation area should be planned to ensure that all passages, including door- ways, elevators, ramps and hallways, are large enough to accommodate the unit and that the floors are strong enough to support the weight. Determine whether any corners or offsets would cause prob- lems in maneuvering the unit.

Liebert recommends removing the exterior side panels, if supplied, before the unit is moved. This will prevent scratches, dents and other damage to the panels.

2

Image 6
Contents Liebert FPC Page Table of Contents Figures Important Safety Instructions Unpacking and Installation Unpacking and Preliminary InspectionHandling Considerations Inch cabinet weight Front Footprint and Floor cable accessCutout Dimensions cooling airflow FrontUnit Preparation Location ConsiderationsSee Notes 2 Front and rear access is required. See Notes 1 Liebert FPC heat outputFull Load Heat Output Unit kVA BTU/Hr kW Floor Pedestal Installation Floor pedestal detailsInput Power Connections Additional Distribution Mounting & WiringPower and Control Wiring Liebert FDC Distribution MountingElectrical connection location for 23 584mm cabinet FPC15000 Rev FPC15002 Rev Suggested minimum input wire size data Main input circuit breaker interrupting rating Low-voltage control junction box dimensions, typical Junction Box InstallationMain input junction box electrical connections 4 wire Main input power junction box dimensions, typicalSystem Grounding Equipment GroundingMinimum grounding electrode conductor size AWG Signal Reference GridGrounding Electrode Conductor for FPCs With Transformer Output VoltageTypical Liebert FPC With transformer grounding arrangement SystemTypical Liebert FPC without transformer groundingOutput Power Connections Liebert FPC Unit EPO Liebert FPC+24VDC MainWiring Low Voltage Terminal StripFactory Typical control wiring for units with monitoring Optional Customer Alarm Inputs SummaryInternal Inspection ChecklistsWarranty StartupBranch circuit breaker torque specifications Torque specifications, generalPanelboard main circuit breaker torque specifications Terminal block compression lug torque specificationsInspection Unit Serial Number Unit Model Number DateStartup Monitoring System Check-Out Customer Alarms Normal System Turn on Startup ProceduresNormal System Shutdown Manual RestartBasic Monitor Panel Units Without Monitoring Power Monitor PanelAlarm Present/Silence FPC16000Operating Instructions Ascii interface default parameters RS-232 Ascii port customer commandsParameter Default Monitored parameters data definitions Field # Data item UnitsInspection and Cleaning RepairInspection Schedule Page Ti n Ne tIti That