Emerson FPC user manual Repair, Inspection and Cleaning, Inspection Schedule

Page 38

Maintenance

5.0MAINTENANCE

5.1Repair

Even the most reliable equipment may fail. Liebert Global Services is at your service to assure fast repair of your unit and minimum downtime of your installation.

! WARNING

Only qualified service personnel should perform maintenance on the Liebert FPC system.

Standard electrical troubleshooting procedures should be used to isolate problems in the unit. If there are questions, don’t hesitate to contact Liebert Global Services.

Repair or replacement of standard items, such as circuit breakers, fuses, transformers, capacitors and indicator lights can either be handled by qualified electricians or referred to Liebert Global Services.

Repairs related to the monitoring system should be referred to Liebert Global Services. To contact LGS for information or repair service in the United States, call 1-800-LIEBERT.

5.2Inspection and Cleaning

Air circulation through the cabinet may cause dust to accumulate on internal components. Cleaning should be done as necessary during electrical inspections.

Annual general system inspections, cleaning, and operation checks are recommended to ensure sys- tem performance and long service life.

! WARNING

Only qualified service personnel should perform maintenance on the Liebert FPC system. All voltage sources to the unit must be disconnected before inspecting or cleaning within the cabinet.

5.2.1Inspection Schedule

It is difficult to establish a schedule for periodic cleanings because conditions vary from site to site. Inspections after the first 24 hours, 30 days and 6 months of operation should help determine a pattern for the inspection schedule.

Electrical connections and component mountings should be inspected after the first 24 hours, 30 days, and 6 months of operation. Inspections should be conducted annually thereafter.

Ventilation openings and grilles should be inspected and cleaned every 6 months to one year.

A complete inspection and operational checkout should be performed annually. This is best done by performing the inspection and start-up procedure as detailed in 3.0 - Inspection and Star- tup Checklist.

LGS offers a complete range of preventive maintenance services. These include thorough equip- ment performance checks and calibration of electronics. Contact Liebert Global Services in the United States by calling 1-800-LIEBERT for details.

34

Image 38
Contents Liebert FPC Page Table of Contents Figures Important Safety Instructions Handling Considerations Unpacking and InstallationUnpacking and Preliminary Inspection Inch cabinet weight Front Footprint and Floor cable accessCutout Dimensions cooling airflow FrontUnit Preparation Location ConsiderationsFull Load Heat Output Unit kVA BTU/Hr kW See Notes 2 Front and rear access is required. See Notes 1Liebert FPC heat output Floor Pedestal Installation Floor pedestal detailsInput Power Connections Additional Distribution Mounting & WiringPower and Control Wiring Liebert FDC Distribution MountingElectrical connection location for 23 584mm cabinet FPC15000 Rev FPC15002 Rev Suggested minimum input wire size data Main input circuit breaker interrupting rating Low-voltage control junction box dimensions, typical Junction Box InstallationMain input junction box electrical connections 4 wire Main input power junction box dimensions, typicalSystem Grounding Equipment GroundingMinimum grounding electrode conductor size AWG Signal Reference GridGrounding Electrode Conductor for FPCs With Transformer Output VoltageTypical Liebert FPC With transformer grounding arrangement SystemTypical Liebert FPC without transformer groundingOutput Power Connections Liebert FPC Unit EPO Liebert FPC+24VDC MainFactory WiringLow Voltage Terminal Strip Typical control wiring for units with monitoring Optional Customer Alarm Inputs SummaryInternal Inspection ChecklistsWarranty StartupBranch circuit breaker torque specifications Torque specifications, generalPanelboard main circuit breaker torque specifications Terminal block compression lug torque specificationsInspection Unit Serial Number Unit Model Number DateStartup Monitoring System Check-Out Customer Alarms Normal System Turn on Startup ProceduresNormal System Shutdown Manual RestartBasic Monitor Panel Units Without Monitoring Power Monitor PanelAlarm Present/Silence FPC16000Operating Instructions Parameter Default Ascii interface default parametersRS-232 Ascii port customer commands Monitored parameters data definitions Field # Data item UnitsInspection Schedule Inspection and CleaningRepair Page Ti n Ne tIti That