Emerson FPC user manual Startup

Page 30

Inspection and Startup Checklist

3.2 Startup

! WARNING

Startup procedures should be performed only by qualified personnel. Hazardous voltages are present in the equipment throughout the majority of the start-up procedure. Use proper safety equipment. proceed with caution.

When opening the main input circuit breaker wait a minimum of one minute before reclosing.

1.Make certain that all circuit breakers are in the OFF position and that power to the unit is locked out.

NOTE

Steps 2 through 6 apply to the Main Input Junction Box. If this installation is not provided with a Main Input Junction Box, proceed to Step 7.

___ 2. Remove the cover of the Main Input Junction Box. Verify proper input power connections to unit, including equipment grounding conductor.

___ 3. Turn ON the building power to the junction box. Check the phase rotation at the junction box. Phase rotation should be A, B, C, as indicated.

___ 4. Check and record the input voltages at the junction box: Volts, Phase A to Phase B = ______________

Volts, Phase B to Phase C = ______________

Volts, Phase C to Phase A = ______________

___ 5. Turn OFF and lock out the building power to the input junction box.

___ 6. Replace the junction box cover.

___ 7. Verify proper input power connections to unit, including equipment grounding conductor and local grounding electrode conductor.

___ 8. Turn ON the building input power to the unit.

___ 9. Check the phase rotation at the main input breaker. Phase rotation should be A, B, C, left-to- right.

___ 10. Check and record the input voltage at the main input breaker. Measured voltages should correspond to the unit’s nameplate input voltage.

Volts, Phase A to Phase B = ______________

Volts, Phase B to Phase C = ______________

Volts, Phase C to Phase A = ______________

___ 11. Turn ON the main input breaker; wait one minute. (If breaker trips OFF, check for wiring errors including control connections. Contact Liebert Global Services or the location factory representative for assistance.)

___ 12. Check the phase rotation at the line side terminals (top) of the panelboard main breaker(s) and any subfeed output circuit breaker(s). The rotation should be A, B, C, left-to-right.

___ 13. Check and record the voltages at the line-side terminals of the output circuit breaker. Measured voltages should correspond to the unit’s nameplate output voltage (within +4%,- 0%).

Volts, Phase A to Phase B = _______________

Volts, Phase B to Phase C = _______________

Volts, Phase C to Phase A = _______________

Volts, Phase A to Neutral = _______________

Volts, Phase B to Neutral = _______________

Volts, Phase C to Neutral = _______________

If output voltage is incorrect, check for wiring errors, incorrect input voltage, or improper trans- former tap. Contact Liebert Global Services at 1-800-LIEBERT in the United States or your local Liebert representative for assistance.

26

Image 30
Contents Liebert FPC Page Table of Contents Figures Important Safety Instructions Unpacking and Installation Unpacking and Preliminary InspectionHandling Considerations Inch cabinet weight Front Footprint and Floor cable accessCutout Dimensions cooling airflow FrontUnit Preparation Location ConsiderationsSee Notes 2 Front and rear access is required. See Notes 1 Liebert FPC heat outputFull Load Heat Output Unit kVA BTU/Hr kW Floor Pedestal Installation Floor pedestal detailsInput Power Connections Additional Distribution Mounting & WiringPower and Control Wiring Liebert FDC Distribution MountingElectrical connection location for 23 584mm cabinet FPC15000 Rev FPC15002 Rev Suggested minimum input wire size data Main input circuit breaker interrupting rating Low-voltage control junction box dimensions, typical Junction Box InstallationMain input junction box electrical connections 4 wire Main input power junction box dimensions, typicalSystem Grounding Equipment GroundingMinimum grounding electrode conductor size AWG Signal Reference GridGrounding Electrode Conductor for FPCs With Transformer Output VoltageTypical Liebert FPC With transformer grounding arrangement SystemTypical Liebert FPC without transformer groundingOutput Power Connections Liebert FPC Unit EPO Liebert FPC+24VDC MainWiring Low Voltage Terminal StripFactory Typical control wiring for units with monitoring Optional Customer Alarm Inputs SummaryInternal Inspection ChecklistsWarranty StartupBranch circuit breaker torque specifications Torque specifications, generalPanelboard main circuit breaker torque specifications Terminal block compression lug torque specificationsInspection Unit Serial Number Unit Model Number DateStartup Monitoring System Check-Out Customer Alarms Normal System Turn on Startup ProceduresNormal System Shutdown Manual RestartBasic Monitor Panel Units Without Monitoring Power Monitor PanelAlarm Present/Silence FPC16000Operating Instructions Ascii interface default parameters RS-232 Ascii port customer commandsParameter Default Monitored parameters data definitions Field # Data item UnitsInspection and Cleaning RepairInspection Schedule Page Ti n Ne tIti That