1.3.6Control Wiring Connections
NEC Article 645 requires that emergency power off (EPO) switches be located at the principal room exits. All standard Liebert power conditioning systems have provisions for external shutdown control from Remote Emergency Power Off (REPO) stations. Figure 14 is a simplified diagram of the shut- down circuitry of the Liebert FPC.
Low-Voltage Control Circuit
Control wiring connections must comply with the NEC and all other applicable codes.
! WARNING
Verify that all incoming
As shown in Figure 14, the control circuit operates on 24VDC. The shutdown device (represented by the REPO switch) activates a
Multiple-Unit Shutdown
When more than one power center is installed by the user, a typical requirement is that actuation of a single device (REPO for example) must shut down all power centers. The
External Control Wiring Connections
External control wiring connections for remote shutdown, alarm, and/or monitoring are made to the
Control wiring connections vary with the type of monitoring system furnished with the unit. Two typ- ical control wiring configurations are shown in Figures 15 and 16.
Figure 14 Simplified shutdown circuit
| Liebert FPC |
| Remote |
|
| ||
|
|
|
| Shutdown |
| ||
|
| +24VDC | 1 | Devices |
|
| |
K5 | K6 |
|
|
|
|
| |
|
|
|
|
|
| ||
|
| Unit EPO | 4 |
|
|
|
|
+ |
|
|
|
|
|
| |
|
|
|
|
|
|
| |
24VDC | Main |
|
| N.O. REPO |
|
| |
Source | Input | K6 | 6 |
|
|
|
|
- | Breaker | Overtemp |
| N.C. REPO |
| ||
Shunt | Switch |
|
| ||||
| Trip | K5 | 2 |
|
|
|
|
|
|
|
| A | 7 | 4 | 1 |
|
|
| 3 |
|
|
| Building |
|
|
|
|
|
| Interface | |
|
|
|
|
|
|
| |
|
|
|
| R1 |
|
| Relay |
|
|
|
| B | 9 | 6 | 3 |
20