Grizzly G0695 owner manual Belt Tensioning, Leadscrews, To tension the V-belt

Page 39

Leadscrews

Lubricant

Frequency

Qty

NLGI #2 Grease

Every

Thin

 

40 Hours

Coat

 

of Operation

 

Use a shop rag and mineral spirits to clean away debris and grime from the longitudinal, cross, and elevation leadscrews and leadscrew nuts. Apply a thin coat of lubricant to the leadscrews, then move the table through the full range of move- ment for each leadscrew to distribute the grease (see Figures 57–58).

Longitudinal

Leadscrew

Figure 57. Longitudinal leadscrew.

Cross

Leadscrew

Vertical

Leadscrew

Figure 58. Cross and vertical leadscrews.

V-Belt Tensioning

Periodically remove the belt cover and inspect the belt for cracking, slipping, or fraying. If the belt shows signs of excessive wear, replace it as outlined in Belt Replacement on Page 41.

However, with normal use, the belt will gradually stretch over time. When it does, perform the fol- lowing procedures to keep it tensioned. No belt deflection is recommended for this belt.

Tools Needed

Qty

Wrench 17mm

1

To tension the V-belt:

1.DISCONNECT MILL FROM POWER!

2.Using a 17mm wrench, loosen the lock bolt, push firmly and hold the belt tension lever toward the rear of the machine and retighten the lock bolt (Figure 59).

Lock Bolt

& Belt

Tension

Lever

V-Belt

Inside

Figure 59. V-belt tension adjustment bolt.

Model G0695 (Mfg. Since 9/10)

-37-

Image 39
Contents Model G0695 VS Milling Machine With RAM Head Page Table of Contents Machine Description IntroductionManual Accuracy Contact InfoIdentification Machine Data Sheet Table Info Hearing PROTECTION. Always wear hear SafetySafety Instructions for Machinery Wearing Proper APPAREL. Do not wearSafety Instructions for Machinery Machine Care and Maintenance Additional Safety Instructions For MillsGlossary of Terms Circuit Requirements 220V Single-Phase OperationDescription Qty SetupNeeded for Setup UnpackingInventory Figure Qty InventoryBefore cleaning, gather the following CleanupSite Considerations Mounting to Shop Floor Moving & Placing MillTo assemble your mill AssemblyUsing Machine Mounts Bolting to Concrete FloorsTest Run Step Spindle Break-InOperations Basic ControlsControl Panel Additional table travel controls Model G0695 Mfg. Since 9/10 Table ControlsDownfeed Controls Table Movement Operation OverviewLimit Stops LocksHeadstock Tilting Tools Needed QtyTo tilt the head Hex Bolt To rotate the turret Headstock Turret RotationTo move the ram inward or outward Headstock Ram MovementCutting Speeds for High Speed Steel HSS Cutting Tools Setting Spindle SpeedSetting Spindle Speed Calculating Spindle SpeedUnloading Tooling Chip CharacteristicsLoading/Unloading Tooling Loading ToolingG1075-52-PC. Clamping Kit AccessoriesG9299-10 Yuasa-Type Rotary Table H8370-Power Feed for MillsG9765-9-PC. Ball End Mill Set H2689-R-8 Quick Change Collet SetG5641-1-2-3 Blocks G9815-Parallel Set H5556-Edge Finder Set G2861-Face Mill G4051-Carbide Insert for Face MillG1054-Dividing Head-BS-1 G5758-Tilt xG5684-R-8 Vertical Collet Rack G5649-5-C Spin IndexModel G5679 Steel Parallel Set G5679-Steel Parallel SetLubrication MaintenanceCleaning Protecting ScheduleLubricant Frequency Qty One-Shot OilerQuill Gearing Vertical Bevel GearsBelt Tensioning LeadscrewsTo tension the V-belt Service TroubleshootingMotor & Electrical Operation Disconnect Mill from Power Before Adjusting the Gibs Adjusting GibsTo replace the V-belt Adjusting Backlash Belt ReplacementPage Wiring Safety Instructions WiringWiring Diagram Electrical Components Control panel wiringBase, Column, & Knee Breakdown Description Base, Column, & Knee Parts ListHead Breakdown Head Parts List Motor & Ram Breakdown Motor & Ram Parts List Table Breakdown Table Parts List Label Placement Comments Warranty CardBOX BELLINGHAM, WA Grizzly INDUSTRIAL, INCWarranty and Returns Warranty and ReturnsOrder Hours a DAY