STEP 3: SOFTWARE INSTALLATION

Quick Installation Guide

Rosemount 3095 MultiVariable

00825-0100-4716, Rev DA October 2009

STEP 3: SOFTWARE INSTALLATION

The 3095 Engineering Assistant (EA) for HART and 3095 Engineering Assistant (EA) for FOUNDATION Fieldbus software programs can be installed on the same computer. The applications cannot be open simultaneously.

3095 Engineering Assistant (EA) for HART Software Installation

1. Install the Program

a.Place the CD-ROM in the drive and run setup.exe from Windows NT, 2000, or XP.

b.After installing the software, install the HART Modem (see “Installing the HART Modem” on page 11).

2. Upgrade the previous versions of Engineering Assistant program (if required)

a.Place the CD-ROM disk 2 into the drive and run the EAUpgrade.exe from Windows 98, NT, 2000, or XP. To properly install, the program will first uninstall Engineering Assistant from the computer. (Upgrades also are available at www.rosemount.com.)

b.Remove the installation disk and reboot the computer to complete installation.

c. To install the upgraded program, run the EAupgrade.exe from Windows 95,98, or NT again.

3. Connect the computer to the 3095 transmitter.

a.Connect the HART modem cable to the computer using the 9-pin serial or USB communications port on the computer.

b.Open the cover above the side marked Field Terminals, and connect the mini-grabbers to the two 3095 terminals marked COMM.

4.Select Engineering Assistant for HART from the program menu. On-Line Mode: EA communicates directly with the 3095 through AMS.

a.In AMS Explorer view or AMS Connection view, right-mouse click on a 3095 device tag or icon.

b.Select SNAP-ON/Linked Apps > Engineering Assistant.

Off-Line Mode: Engineering Assistant does not communicate directly with the 3095. Instead, the EA configuration is sent to a 3095 later when Engineering Assistant is in on-line mode. In the off-line mode a future device needs to be created in order to launch Engineering Assistant.

a.In AMS Explorer view or AMS Device Connection view, left click on Plant Database to the Area folder.

b.Left click on Area to the Unit folder.

c. Left click on Unit to the Equipment Module folder.

d.Left click on Equipment Module to the Control Module folder. e.right-mouse click on Control Module to the pop-up context menu. f. Select Add Future Device.

g.Select 3095MV Template and click OK.

h.Right-mouse click on Future device to pop-up context menu. i. Select SNAP-ON/Linked Apps > Engineering Assistant.

10

Image 10
Contents Fieldbus Protocol Rosemount 3095MF Series Flowmeter Transmitter Quick Installation GuideRosemount 3095 MultiVariable ¢00825-0100-4716/¤Electrical shock can result in death or serious injury Explosions could result in death or serious injuryProcess leaks may cause harm or result in death IMPORTANT NOTICETerminal Block HART O-ring Cover TRANSMITTER EXPLODED VIEWRTD Connector Certification Label Electronics Board Nameplate Module O-ringGas Flow Applications STEP 1 MOUNT THE TRANSMITTERLiquid Flow Applications Steam Flow ApplicationsConsider Housing Rotation STEP 2 TRANSMITTER INSTALLATIONField Installation Figure 2. Alarm Jumper Location STEP 2 CONTINUEDFigure 3. Armored Shielded RTD Cable Figure 4. Shielded RTD Cable Cable Adapter 1/2-14 NPT Black Cable ConnectorCable Gland Black Cable Connector/ RTD Connector Figure 5. ATEX/IECEx Flameproof RTD CableBolting Considerations Figure 6. Common Transmitter AssembliesO-ring O-rings with Flange AdaptersFlange Adapter PTFE BasedSTEP 3 SOFTWARE INSTALLATION 3095 Engineering Assistant EA for HART Software InstallationSTEP 3 CONTINUED Installing the HART Modem3095 Engineering Assistant EA for FOUNDATION Fieldbus 3. Select Hart ModemSTEP 4 CONNECT WIRING AND POWER UP HART 24 Vdc Supply Current RL≥ 250Ω MeterPower Conditioner STEP 4 CONNECT WIRING AND POWER UP FIELDBUSPower Supply Shield Wire GroundSend the Configuration to the Transmitter STEP 5 CONFIGURE THE TRANSMITTER HARTSetting the Loop to Manual Basic Configuration ParametersFunction/Variable To configure the AI Block STEP 5 CONFIGURE THE TRANSMITTER FIELDBUSAI Block configuration parameters Using the Foundation Fieldbus Host System Using the Field CommunicatorUsing the Foundation Fieldbus AI Block STEP 6 TRIM THE TRANSMITTEREuropean Directive Information PRODUCT CERTIFICATIONS Rosemount 3095 with HARTApproved Manufacturing Locations Rosemount 3095 HART Hazardous Locations CertificationsEuropean Certifications Canadian Standards Association CSASpecial Conditions for Safe Use IECEx Certifications HART Conditions of Certification INMETRO CertificationsSpecial conditions for safe use China NEPSI CertificationsL i ≈ Maximum Temperature of ATEX Directive 94/9/EC Rosemount 3095 with FieldbusCombinations of Certifications European Pressure Equipment Directive PED 97/23/ECFM Approvals Rosemount 3095 Fieldbus Hazardous Locations CertificationsNorth American Certifications Canadian Standards Association CSASpecial conditions for safe use IECEx Certifications Fieldbus Rosemount 3095 MultiVariable Quick Installation GuideCombinations of Certifications Quick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariable