STEP 4: CONNECT WIRING AND POWER UP (HART)

Quick Installation Guide

Rosemount 3095 MultiVariable

00825-0100-4716, Rev DA October 2009

STEP 4: CONNECT WIRING AND POWER UP (HART)

Use the following steps to wire the transmitter:

1.Remove the housing cover on the side marked FIELD TERMINALS.

2.Connect the signal leads to the terminals.

NOTE

Do not connect the powered signal wiring to the test terminals. Power could damage the test diode in the test connection. Shielded twisted pair cable should be used for best results. Use 24 AWG or larger wire and do not exceed 5,000 feet (1500 meters).

3.Plug and seal unused conduit connections.

4.Install wiring with a drip loop. Arrange the drip loop so the bottom is lower than the conduit connections and the transmitter housing.

5.Replace the housing cover.

Figure 8 shows wiring connections necessary to power a 3095 and enable communications with a hand-held HART communicator.

Figure 8. Transmitter Wiring Diagrams (4–20 man Power Supply)

24 Vdc Supply

24 Vdc SupplyManual backgroundManual backgroundManual backgroundManual background Current RL250Ω

Manual backgroundManual backgroundManual backgroundManual backgroundManual background Meter

Installation of the transient protection terminal block does not provide transient protection unless the 3095 case is properly grounded.

The dc power supply should provide power with less than two percent ripple. The total resistance load is the sum of the resistance of the signal leads and the load resistance of the controller, indicator, and related pieces. Note that the resistance of intrinsic safety barriers, if used, must be included.

Figure 9. Load Limitation

Max. Loop Resistance = Power Supply Voltage-11.0

2000

0.022

 

Load (Ohms)

 

Operating

 

250

 

Region

 

0

16.5(2)

42.4(1)

 

11.0

55

 

Power Supply

 

(1)For CSA approval, power supply must not exceed 42.4 Vdc.

(2)HART protocol communication requires a loop resistance value between 250-1100 ohms, inclusive.

12

Image 12
Contents Quick Installation Guide Rosemount 3095 MultiVariableFieldbus Protocol Rosemount 3095MF Series Flowmeter Transmitter ¢00825-0100-4716/¤Explosions could result in death or serious injury Process leaks may cause harm or result in deathElectrical shock can result in death or serious injury IMPORTANT NOTICETRANSMITTER EXPLODED VIEW RTD ConnectorTerminal Block HART O-ring Cover Certification Label Electronics Board Nameplate Module O-ringSTEP 1 MOUNT THE TRANSMITTER Liquid Flow ApplicationsGas Flow Applications Steam Flow ApplicationsSTEP 2 TRANSMITTER INSTALLATION Consider Housing RotationField Installation STEP 2 CONTINUED Figure 2. Alarm Jumper LocationFigure 3. Armored Shielded RTD Cable Cable Adapter 1/2-14 NPT Black Cable Connector Cable Gland Black Cable Connector/ RTD ConnectorFigure 4. Shielded RTD Cable Figure 5. ATEX/IECEx Flameproof RTD CableBolting Considerations Figure 6. Common Transmitter Assemblies O-rings with Flange Adapters Flange Adapter O-ring PTFE BasedSTEP 3 SOFTWARE INSTALLATION 3095 Engineering Assistant EA for HART Software InstallationInstalling the HART Modem 3095 Engineering Assistant EA for FOUNDATION FieldbusSTEP 3 CONTINUED 3. Select Hart ModemSTEP 4 CONNECT WIRING AND POWER UP HART 24 Vdc Supply Current RL≥ 250Ω MeterSTEP 4 CONNECT WIRING AND POWER UP FIELDBUS Power SupplyPower Conditioner Shield Wire GroundSTEP 5 CONFIGURE THE TRANSMITTER HART Setting the Loop to ManualSend the Configuration to the Transmitter Basic Configuration ParametersQuick Installation Guide STEP 5 CONFIGURE THE TRANSMITTER FIELDBUS To configure the AI BlockAI Block configuration parameters Using the Field Communicator Using the Foundation Fieldbus AI BlockUsing the Foundation Fieldbus Host System STEP 6 TRIM THE TRANSMITTERPRODUCT CERTIFICATIONS Rosemount 3095 with HART Approved Manufacturing LocationsEuropean Directive Information Rosemount 3095 HART Hazardous Locations CertificationsCanadian Standards Association CSA European CertificationsSpecial Conditions for Safe Use IECEx Certifications HART Conditions of Certification INMETRO CertificationsChina NEPSI Certifications Special conditions for safe useL i ≈ Maximum Temperature of Rosemount 3095 with Fieldbus Combinations of CertificationsATEX Directive 94/9/EC European Pressure Equipment Directive PED 97/23/ECRosemount 3095 Fieldbus Hazardous Locations Certifications North American CertificationsFM Approvals Canadian Standards Association CSAQuick Installation Guide IECEx Certifications Fieldbus Quick Installation Guide Rosemount 3095 MultiVariableCombinations of Certifications Quick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariableQuick Installation Guide Rosemount 3095 MultiVariable