Unit Start-Up with WSHP Open Controls

The WSHP Open is a multi-protocol (default BACnet*) con- troller with extensive features, flexible options and powerful capabilities. The unit comes from the factory pre-programmed and needs minimal set up to function in a BAS (Building Auto- mation System) system or provide additional capabilities to Carrier's WSHP product line. Most settings on the controller have factory defaults set for ease of installation. There are a few settings that must be configured in the field and several set- tings that can be adjusted if required by unique job conditions. Refer to Appendix A — WSHP Open Screen Configuration. In order to configure the unit, a BACview6 display is required. See Fig. 35.

NOTE: If the WSHP Open control has lost its programming, all display pixels will be displayed on the SPT sensor. See the WSHP Third Party Integration Guide.

When the unit is OFF, the SPT sensor will indicate OFF. When power is applied, the SPT sensor will indicate tempera- ture in the space at 78 F.

To start-up a unit with WSHP Open controls:

1.To plug in the BACview6 handheld display into a SPT sensor, point the two ears on the connector up and tilt the bottom of the plug toward you. Insert the plug up into the SPT sensor while pushing the bottom of the plug away from you.

2.BACview6 should respond with "Establishing Connec- tion." The Home screen will then appear on the display showing operating mode and space temperature. Press any button to continue.

See Appendix A — WSHP Open Screen Configuration for the hierarchal structure of the WSHP Open controller. All functions of the controller can be set from the Home screen.

3.When the Login is requested, type 1111 and push the OK softkey. The Logout will then be displayed to indicate the password was accepted.

4.To set the Clock if it is not already displayed:

a.Select System Settings from the Home screen, then press Clockset.

b.Scroll to hour, minute and second using the arrow keys. Use the number keypad to set actual time.

c.Scroll to day, month and year using arrow keys. Use number keypad to set date.

5.To set Daylight Savings Time (DST):

a.Push the DST softkey. The display will indicate 02:00:060 which is equal to 2:00AM.

b.To program the beginning and end dates, scroll down to the beginning month and press the enter key. The softkeys (INCR and DECR) will activate to increment the month in either direction, Jan, Feb, March, etc.

c.Use number keys to select the day of month and year.

d.Push the OK softkey to finalize the data.

6.To view configuration settings:

a.Select the Config softkey.

b.Select the Service Config softkey. Scroll through the factory settings by using the up and down arrow keys. See below for factory settings.

Only the following settings will need to be checked.

# of Fan Speeds — This should be set to "1" for units with PSC motors and set to "3" for units with ECM motors.

Compressor Stages — This should be set to "1."

Factory Dehumidification Reheat Coil — This should be set to "none" unless the modulating hot water reheat option is supplied in the unit, then set to "installed."

The condenser water limit needs to be verified depending on design parameters and application, whether geothermal or boiler/tower.

7.To view unit configuration settings:

a.Select the Unit Configuration softkey, then select Unit.

b.Scroll through the unit settings by using the up and down arrow keys. Unit settings include:

Fan Mode: Default Continuous

Fan Delay:

Minimum SAT Cooling: Default 50 F

Maximum SAT Heating: Default 110 F

Filter Service Alarm: Must be set from 0 to 9999 hr

8.To set local schedules:

a.Select the Schedule softkey from the Configuration screen, then press enter.

b.Select Weekly, then press enter (7 schedules available).

c.Select day and press enter.

d.Press enter again and select ADD or DEL (DECR or INCR) set schedule.

e.Enter ON/OFF time, then press continue.

Fig. 35 — BACview6 Display Interface

*Sponsored by ASHRAE (American Society of Heating, Refrigerat- ing and Air Conditioning Engineers).

40

Image 40
Contents Installation, Start-Up, Service Instructions ContentsInstallation Safety ConsiderationsGeneral Physical Data 50PSH, PSV, PSD018-070 Units Typical Installation 50PSH Unit ASP BSPCAP Code Return Discharge CSP50PSV Dimensional Data A50-7846ef HWR Hot Water Reheat Left Hand Right HandSide Discharge Back DischargeInstall Condensate Drain Mount the UnitTrap Condensate Drain Connection Open Loop and Recirculating Well Water Quality GuidelinesMaterial Typical Ground-Water Piping Installation Metal Hose Minimum Bend RadiiWire Field Power Supply Supply/Return Hose KitComplete C Controller Fault Codes Description of Operation LED Alarm RelayTrans AstatWire Number BMCCompr Yellow REDECM LWTA50-8363 Units with ECM, Complete C and LON Controller 460A50-8364 Units with ECM, Deluxe D and LON Controller 460Hpws SATMves WHSP-OPEN A50 83548356 LWT A50-8380 Wshp Open Control50PSH, PSV, PSD Electrical Data PSC Motor 50PSH, PSV, PSD Electrical Data PSC High-Static Motor50PSH, PSV, PSD Electrical Data, ECM Motor Wire Field Controls Low Voltage Field WiringRnet Wiring Specifications A50-8441A50-8442 Field-Supplied Sensors for Wshp Open ControllerRnet Wiring Wire TerminalOperate ECM Interface Board A50-8443Setting Size ECM Blower Motor Performance DataRated MIN FAN Unit Airflow CFM Speed SizeCoil Units with Reheat ESP Loss Face Velocity FPMComplete C Control Jumper Settings Deluxe D Control Jumper SettingsPRE-START-UP Field Selectable InputsDIP Switch Block S2 Accessory 1 Relay Options DIP Switch Block S2 Accessory 2 Relay OptionsHumidistat/Dehumidistat Logic Deluxe D DIP Switch Settings VACHWR Operating Modes A50-8145Unit Start-Up Cooling Mode START-UPOperating Limits Operating Limits 50PSH, PSV, PSD UnitsUnit Start-Up Heating Mode Water Temperature Change Through Heat ExchangerCooling Heating Water Flow Rate GPM Rise F Drop F Water Flow TempGPM/ton Pressure Heat Cooling Rise Drop Psig Flow Flow Unit Start-Up with Wshp Open Controls BACview6 Display Interface50PSH, PSV, PSD Water Water Temperature F Flow 50PSH, PSV, PSD Coaxial Water Pressure DropUnit Size GPMApproximate Fluid Volume gal Per 100 Ft of Pipe Antifreeze Percentages by VolumeOperation Units with Aquazone Complete C ControlUnits with HWR Option Units with Wshp Open Multiple ProtocolPage Page Complete C and Deluxe D Board System Test LED Status Description of Operation Alarm RelayOff Complete C Control LED Code Fault Descriptions LED Code Fault DescriptionAquazone Deluxe D Control LED Indica Description Status LED Test LEDService Troubleshooting Refrigerant ChargingAir Coil Fan Motor Removal Replacing the Wshp Open Controller’s BatFP1 and FP2 Thermistor Location Page ECM Troubleshooting Fault Description SolutionECM Pin Connectors A50-8448ECM Troubleshooting Flow Diagram A50-8447Wshp Troubleshooting Fault Heating Cooling Possible Cause SolutionGood Practices TXVCondensate Fault Code 7 Auto ResettingNo Fault Code Shown CodeTemperature in Heating High Head PressureLow Suction Pressure Low Discharge AirAppendix a Wshp Open Screen Configuration Appendix a Wshp Open Screen Configuration Set Points Weekly ScheduleException Schedules 1Service Appendix a Wshp Screen Open ConfigurationTest Point Name Password Editable Range Default Level Configuration ServiceScreen Name Alarm LinkagePage Page Copyright 2009 Carrier Corporation 50PSH,PSV,PSD START-UP Checklist II. START-UPHeating Cycle Analysis Cooling Cycle AnalysisA50-8494 A50-8495