MAINTENANCE OVERVIEW

This section describes the daily, weekly, monthly and semi- annual maintenance schedules that should be performed when changing materials or lines, or when changing equipment, as well as the maintenance procedures to follow.

Cutting either flexible or rigid materials generates tremendous shock and vibration to the entire unit. Anything that can loosen, will over time.

To maintain the best performance, follow this maintenance schedule and develop an effective preventative maintenance program.

PREVENTATIVE

MAINTENANCE

SCHEDULE

Daily

Checking saw blade(s)

Clean, sharpen or replace as needed (see Section 4, Blade Replacement.)

Inspecting the blade mounting hardware

The blade securing bolt should use both a lock washer and flat washer, and be tightened enough to fully com- press the lock washer. Replace the holding pins if they appear worn.

Inspecting the the saw product guides for wear and alignment.

Inspecting saw alignment

Proper saw alignment is critical for optimum perfor- mance. Use a plumb line or laser to check for a straight line from the extrusion die to the saw bush- ings.

Check floor locks

It is always recommended that the weight be removed from the casters for optimum stability during cutting cycles. Check to see if the floor locking mechanism is properly adjusted.

5-4

MAINTENANCE

CTS Saw

UGE058/0803

Image 42
Contents Traveling Saw Date Document Number Table of Contents Troubleshooting Introduction Purpose User Guide HOW the User Guide is OrganizedYour Responsibility AS a User Read this SO no ONE Gets Hurt Read this SO no ONE Gets Hurt HOW to USE Lockout Device Turn the rotary disconnect switch to OFF or O positionPage Description What is Typical ApplicationsHOW the CTS SAW Works SAW Works Features CTS SAWSpecifications Optional Equipment Left to right machine operationPage Installation Unpacking the Boxes Carefully uncrate the saw and its componentsPreparing for Installation You need these tools for installationPositioning the CTS SAW Move the saw into position. Place the saw in posiDetermine the best distance from the belt puller to Position the SAW Connecting Main Power Source Installing the Encoder Installing the SAW Blades Remove the hex nutPreparing for Testing Testing the InstallationPage Operation SAW Control Control Features Blade Height Adjustment Machine Frame Support SystemTo remove and/or adjust each clamp assembly Upper Clamp AdjustmentPower Supply Control PanelsPneumatic Cylinder Operation Electrical Operation Machine Lubrication System InspectionBlade Replacement Wait at least five minutes for the blade to stop completelyChip Collection Shrouds Blower Connection Maintenance Maintenance Features Maintenance Checking saw blades Maintenance OverviewPreventative Maintenance Schedule Inspecting the blade mounting hardwareWeekly Checking Blades Checking Electrical Connections Open the electrical enclosure Close the electrical enclosure doorTroubleshooting Before Beginning FEW Words of CautionIdentifying Cause of a Problem Electrical Problems Symptom Possible cause SolutionIncorrect cooling Product Quality ProblemsIncorrect blade design ExtrudateRodless cylinder problem Problem Puller problemCounter problem Solenoid problemChecking Servo Amplifier Check the encoder cable for damage. If neces Checking the EncoderCheck all connections Check the encoder itself. There should be no playWE’RE Here to Help From outside the United States, callAppendix A-2 Conair Servo Traveling Saw Soft KeysNumeric keys Fixed Function Keys at BottomLCD Screen Contents Power Up Sequence Starting CommsMain Screen Length CounterOn/Off Softkey Total Screen Reset SoftkeyTotal Softkey Exit SoftkeyLength Softkey Enter or Delete?Homing Home SeekHome Already Menu Area Maint. SoftkeyMaint. Area R c t n S o f t k e yChange Softkey S o f t k e y Time SoftkeyCycles Softkey B l e S o f t k e yT u r n S o f t k e y Acceptable range is 120.00-1800.00 ipmV a n c e S o f t k e y 20%Error Message Menu Area Factory SoftkeyTable Assembly, Pneumatic / Servo GeneralBlades Opt Equipment Parts List To Order Parts Call Toll Free 800 Servo Opt. / Table TravelElectrical Control, 3hp 230/460v Volt