Conair CTS 9, CTS 7, CTS 5 manual Preparing for Testing, Testing the Installation

Page 27

1

Make sure all components are installed according

 

to assembly drawings. Make sure that all bolts on the saw

 

have been tightened.

 

 

2

Check that saw is firmly locked into position with

 

the anchoring screws.

 

 

3

Check that all wiring conforms to electrical

 

codes, and all wiring covers are in place.

 

 

4

Plug in the air supply

PREPARING FOR TESTING

1

2

3

Turn on the main disconnect. Plug in the main

power cord and turn on the main disconnect.

Check that the E-Stop button is in the out, extended position.

Press the vacuum start button.

Check the rotation of the vacuum motor for correct phas- ing. (The phase in your plant may be different from the Conair factory.)

TESTING THE INSTALLATION

4

5

Press the saw start button.

Turn off the saw and vacuum.

Check the saw blade rotation.

The top of the saw blade should turn towards the front or operator side. If the top of the blade is spinning away from you or the operator side switch one of the 3-phase plug wires. Then recheck the blade rotation.

6

Make a sample cut. Restart the vacuum and the saw motor and press the manual cut button. The saw should make one sample cut.

If the saw is not working properly at any time, turn it off immediately and refer to the Troubleshooting section of this User Guide.

If you do not encounter any problems, proceed to the Operation section.

UGE058/0803

CTS Saw INSTALLATION

3-9

Image 27
Contents Traveling Saw Date Document Number Table of Contents Troubleshooting Introduction Purpose User Guide HOW the User Guide is OrganizedYour Responsibility AS a User Read this SO no ONE Gets Hurt Read this SO no ONE Gets Hurt Turn the rotary disconnect switch to OFF or O position HOW to USE Lockout DevicePage Description Typical Applications What isHOW the CTS SAW Works SAW Works CTS SAW FeaturesSpecifications Left to right machine operation Optional EquipmentPage Installation Carefully uncrate the saw and its components Unpacking the BoxesYou need these tools for installation Preparing for InstallationPositioning the CTS SAW Move the saw into position. Place the saw in posiDetermine the best distance from the belt puller to Position the SAW Connecting Main Power Source Installing the Encoder Remove the hex nut Installing the SAW BladesTesting the Installation Preparing for TestingPage Operation SAW Control Control Features Machine Frame Support System Blade Height AdjustmentControl Panels Upper Clamp AdjustmentPower Supply To remove and/or adjust each clamp assemblyPneumatic Cylinder Operation Electrical Operation System Inspection Machine LubricationWait at least five minutes for the blade to stop completely Blade ReplacementChip Collection Shrouds Blower Connection Maintenance Maintenance Features Maintenance Inspecting the blade mounting hardware Maintenance OverviewPreventative Maintenance Schedule Checking saw bladesWeekly Checking Blades Checking Electrical Connections Close the electrical enclosure door Open the electrical enclosureTroubleshooting FEW Words of Caution Before BeginningIdentifying Cause of a Problem Symptom Possible cause Solution Electrical ProblemsExtrudate Product Quality ProblemsIncorrect blade design Incorrect coolingSolenoid problem Problem Puller problemCounter problem Rodless cylinder problemChecking Servo Amplifier Check the encoder itself. There should be no play Checking the EncoderCheck all connections Check the encoder cable for damage. If necesFrom outside the United States, call WE’RE Here to HelpAppendix A-2 Soft Keys Conair Servo Traveling SawNumeric keys Fixed Function Keys at BottomLCD Screen Contents Starting Comms Power Up SequenceMain Screen Length CounterOn/Off Softkey Exit Softkey Reset SoftkeyTotal Softkey Total ScreenEnter or Delete? Length SoftkeyHome Seek HomingHome Already Maint. Softkey Menu AreaMaint. Area R c t n S o f t k e yChange Softkey Time Softkey S o f t k e yB l e S o f t k e y Cycles SoftkeyAcceptable range is 120.00-1800.00 ipm T u r n S o f t k e y20% V a n c e S o f t k e yMenu Area Factory Softkey Error MessageTable Assembly, Pneumatic / Servo GeneralBlades Opt Servo Opt. / Table Travel Equipment Parts List To Order Parts Call Toll Free 800Volt Electrical Control, 3hp 230/460v