START-UP CHECKLIST
(Fill out this form on
I. PRELIMINARY INFORMATION:
50BV UNIT: MODEL NO. ____________________ SERIAL NO. ____________________
II. PRE-START-UP:
VERIFY ALL SHIPPING MATERIALS HAVE BEEN REMOVED FROM THE UNIT |
| ||
IS THERE ANY SHIPPING DAMAGE? ________________ | IF SO, WHERE ________________ | ||
_________________________________________________________ |
|
| |
WILL THIS DAMAGE PREVENT UNIT | (Y/N) _______ |
| |
CHECK POWER SUPPLY. DOES IT AGREE WITH UNIT? (Y/N) _______ |
| ||
HAS THE GROUND WIRE BEEN CONNECTED? | (Y/N) _______ |
| |
HAS THE CIRCUIT PROTECTION BEEN SIZED AND INSTALLED PROPERLY? (Y/N) _______ | |||
ARE THE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY? (Y/N) _______ | |||
HAS THE CORRECT INPUT POWER PHASE SEQUENCE BEEN CONFIRMED WITH A METER? (Y/N) _______ | |||
HAS THE FAN AND MOTOR PULLEY BEEN CHECKED FOR PROPER ALIGNMENT |
| ||
AND DOES THE FAN BELT HAVE PROPER TENSION? |
| (Y/N) _______ |
|
HAS WATER BEEN PLACED IN DRAIN PAN TO CONFIRM PROPER DRAINAGE? (Y/N) _______ | |||
ARE PROPER AIR FILTERS IN PLACE AND CLEAN? |
| (Y/N) _______ |
|
VERIFY THAT THE UNIT IS INSTALLED WITHIN LEVELING TOLERANCES | (Y/N) _______ | ||
CONTROLS |
|
|
|
HAS THE DUCT STATIC PRESSURE PROBE BEEN INSTALLED? | (Y/N) _______ |
| |
HAVE CONTROL CONNECTIONS BEEN MADE AND CHECKED? | (Y/N) _______ |
| |
ARE ALL WIRING TERMINALS (including main power supply) TIGHT? (Y/N) _______ |
| ||
HAS AUTOMATIC RUN TEST BEEN COMPLETED? |
| (Y/N) _______ |
|
HAS THE VFD CHECKOUT BEEN COMPLETED? |
| (Y/N) _______ |
|
PIPING
HAVE LEAK CHECKS BEEN MADE AT COMPRESSOR, CONDENSER, EVAPORATOR, TXVs (Thermostatic Expansion Valves), SOLENOID VALVES, FILTER DRIERS, AND FUSIBLE PLUGS WITH A LEAK DETECTOR? (Y/N) _______
HAVE WATER AND STEAM VALVES BEEN OPENED (to fill piping and heat exchangers)?(Y/N) _______
HAS AIR PURGE BEEN PERFORMED? (Y/N) _______ |
|
|
|
|
|
| ||||
ELECTRICAL |
|
|
|
|
|
|
|
|
| |
CHECK VOLTAGE IMBALANCE |
|
|
|
|
|
|
|
|
| |
| V | AC |
|
|
| V | BC |
| V | |
(AB + AC + BC)/3 = AVERAGE VOLTAGE = |
|
|
| V |
|
|
| |||
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE = |
|
|
| V |
| |||||
VOLTAGE IMBALANCE = 100 X (MAX DEVIATION)/(AVERAGE VOLTAGE) = | % (IF OVER 2% VOLT- |
AGE IMBALANCE, DO NOT ATTEMPT TO START SYSTEM; CALL LOCAL POWER COMPANY FOR ASSISTANCE.)