Carrier 50BV020-064 specifications CV Units LED Diagnostic Codes, Forcing an Input or Output

Page 54

Table 29 — CV Units LED Diagnostic Codes

NO. OF BLINKS

DESCRIPTION

1

1st Stage High-Pressure Lockout

2

1st Stage Low-Pressure Lockout

3

2nd Stage High-Pressure Lockout

4

2nd Stage Low-Pressure Lockout

5

Freeze Protection Lockout*

6

Condensate Overflow Lockout*

*Freeze protection and condensate overflow lockout require optional sensors.

NOTE: The main control board has a red LED (light-emitting diode) for fault indication and will blink a code as described above. Count the number of blinks to determine the lockout condition.

Forcing and Clearing an Input or Output (VAV Only) — During unit operation and/or troubleshooting, it may be necessary or desirable to clear an input or output. Tables 30 and 31 describe the procedure for forcing and clear- ing inputs and outputs.

Table 30 — Forcing an Input or Output

 

STEP NO. INSTRUCTION/ACTION

RESULT

1.

Press 3, SET, ENTER.

“Controller Password”

2.

Press ENTER.

“Log in to Controller” “Enter Password”

3.

Press 1111, ENTER.

“Log in to Controller” “Logged in”

4.

Press STAT.

“Hardware Points”

5.

Press ENTER.

“Supply Air Temperature”

6.

Press down arrow to obtain desired item.

(NOTE: Order is PCB1 I/O, PCB2 I/O, PCB3 I/O.)

7. Key in force value (1=on/start, 0 = off/stop), ENTER.

Force value/status “Service”

Table 31 — Clearing a Forced Input or Output

 

STEP NO. INSTRUCTION/ACTION

RESULT

1.

Press 3, SET, ENTER.

“Controller Password”

2.

Press ENTER.

“Log in to Controller” “Enter Password”

3.

Press 1111, ENTER.

“Log in to Controller” “Logged in”

4.

Press STAT.

“Hardware Points”

5.

Press ENTER.

“Supply Air Temperature”

6.

Press down arrow to obtain desired item.

(NOTE: Order is PCB1 I/O, PCB2 I/O, PCB3 I/O.)

7. Press CLEAR, ENTER.

Auto value/status (NOTE: “Service” must be gone.)

54

Image 54
Contents Installation, Start-Upand Service Instructions CONTENTSSAFETY CONSIDERATIONS MAJOR SYSTEM COMPONENTS Constant Volume CV Units GENERALTable 2 - Modular Unit Shipping Table INSTALLATIONStep 1 - Complete Pre-InstallationChecks a50-7257efFig. 2 - 50BVC,J,Q020-034Dimensions Fig. 3 - 50BVE,K020-034Dimensions Fig. 4 - 50BVT,V,W034 High-BoyDimensions a50-8201Fig. 5 - 50BVT,V,W034 Low-BoyDimensions Fig. 6 - 50BVT,V,W044-064 High-BoyDimensions Fig. 7 - 50BVT,V,W044-064 Low-BoyDimensions Fig. 8 - 50BVU,X034 High-BoyDimensions Fig. 9 - 50BVU,X034 Low-BoyDimensions Fig. 10 - 50BVU,X044-064 High-BoyDimensions Fig. 11 - 50BVU,X044-064 Low-BoyDimensions NOTES 1.Dimensions in inches mm a50-7306efNOTES 1.Dimensions in inches mm a50-7307efShipping Weights lb a50-8235Size 034 Units Size 044-064Units Table 3A - Physical Data - 50BVC,E,J,K,Q Table 3B - Physical Data - 50BVT,U,V,W,X Fig. 15 - Typical Fan Discharge Connections for Multiple Fan UnitsP/N 39EK20462 a50-7138efFig. 16 - Duct Static Pressure Probe a50-7267efa50-8253 Fig. 19 - DHS Limit Switch P/NStep 4 - Make Piping Connections Fig. 18 - DHS Pressure Limit LocationTable 5B - Condenser Pressure Drop Table 5A - Condenser Pressure Drop50BVC,J,Q Units 50BVT,V,W UnitsTable 6B - Hot Water Pressure Drop Table 6A - Hot Water Pressure Drop50BVC,E,J,K,Q Units 50BVT,U,V,W,X Unitsft wg, 50BVT,U,V,W,X Units Step 5 - Complete Electrical ConnectionsTable 7B - Economizer Pressure Drop Curve a50-7270efTable 9A - Electrical Data - 50BVC,E,J,K,Q Table 9B - Electrical Data - 50BVT,U,V,W,X Fig. 24 - Typical Wiring 18 to 30 Ton Units a50-7272efTwo-StageCooling Units a50-7164tf a50-7273efTable 10 - Recommended Cables Fig. 26 - Field Terminal BlockFig. 27 - Modular Unit VAV Control Panel Installation Unit Discharge Locationa50-7275ef a39-1867tValues for Supply-AirTemperature Sensor START-UPTable 11 - Thermistor Resistance vs Temperature 10 Kilo- ohmCV Unit Start-Up Table 13 - Fan Performance - 50BVC,E,Q020Table 14 - Fan Performance - 50BVC,E,Q024 Table 15 - Fan Performance - 50BVC,E,Q028 Table 16 - Fan Performance - 50BVC,E,Q034 Table 17 - Fan Performance - 50BVT,U,V034 Table 17 - Fan Performance - 50BVT,U,V034 cont Table 18 - Fan Performance - 50BVT,U,V044 Table 19 - Fan Performance - 50BVT,U,V054 Table 19 - Fan Performance - 50BVT,U,V054 cont Table 20 - Fan Performance - 50BVT,U,V064 Table 20 - Fan Performance - 50BVT,U,V064 cont VAV Unit Start-Up Fig. 32 - LID OMNIZONE VPAC02-06-04 a50-7425efFig. 33 - 50BV VFD Display The LID display will show Year Table 21 - Controller Set Points Table 22 - Controller Hardware PointsTable 23 - Software Points Table 24 - Configuration Parameters Unoccupied space or return air temperature demand SERVICE MAINTENANCEa50-187tf a50-186tfFig. 34 - Gravity Flow Method Fig. 35 - Forced Circulation MethodCharging the System Evaporator Fan Performance AdjustmentTROUBLESHOOTING a50-7135tfPROBLEM POSSIBLE CAUSECORRECTION PROCEDURE Table 28 - Unit TroubleshootingPROBLEM POSSIBLE CAUSETable 29 - CV Units LED Diagnostic Codes Table 30 - Forcing an Input or OutputTable 31 - Clearing a Forced Input or Output Page Page Page Page FIELD WIRING UNIT WIRINGPage a50-7282ef FIELD WIRINGWIRE LEGEND TRANS-1FIELD WIRING PCB2 J1FIELD WIRING UNIT WIRINGPCB1 FIELD WIRING PCB1LEGEND AND NOTES FOR FIG Form 50BV-3SI Copyright 2008 Carrier CorporationCatalog No 10-08II. PRE-START-UP START-UPCHECKLISTI. PRELIMINARY INFORMATION CONTROLSIII.START-UP