HP xw2x220c Blade manual Specification Value

Page 49

Specification

Value

 

 

Rated input voltage

200 VAC to 220 VAC line-to-line

 

3-phase Delta

 

 

Rated input frequency

50 Hz to 60 Hz

 

 

Rated input power per power

7836VA

cord (maximum)

 

 

 

Three-phase HP 2400W High Efficiency Power Supply specification (North America/Japan)

Specification

Value

 

 

Power cords (2)

NEMA L15-30p

 

2.44 m (10 ft)

 

 

Max input current per line cord

24.0A at 200 VAC

 

23.1A at 208 VAC

 

 

Input requirements

 

 

 

Rated input voltage

200 VAC to 220 VAC line-to-line

 

3-phase Delta

 

 

Rated input frequency

50 Hz to 60 Hz

 

 

Rated input power per power

8340VA

cord (maximum)

 

 

 

Three-phase HP 2250W Power Supply specification (International)

Specification

Value

 

 

Power cords (2)

IEC-309 200/346-V to 240/415-V, 5-pin,

 

16-A

 

 

2.44 m (10 ft)

 

 

 

Max input current per line cord

11.9

A at 220 VAC

 

10.9

A at 240VAC

 

 

Max input power per line cord

7836 VA Maximum

 

 

 

Input requirements

 

 

 

 

Rated input voltage

346 VAC to 415 VAC line-to-line

 

200 VAC to 240 VAC line-to-neutral

 

3-phase WYE

 

 

Rated input frequency

50 Hz to 60 Hz

 

 

 

Power requirements and considerations 49

Image 49
Contents HP BladeSystem c-Class Site Planning Guide Intended audience Contents Conversion factors and formulas Technical support About this document IntroductionRelated documentation Ashrae guidelines for site planning General site preparation guidelinesHP site planning assistance Computer room preparation Site planning considerationsPage Basic air distribution systems Air conditioning system specificationsAir conditioning ducts Cabling requirementsRaised floor loading Floor loadingAverage floor loading Installation and maintenance precautions Computer room safetyFire protection Fire suppressionLighting requirements for equipment servicing Working space for component accessEnvironmental elements Environmental requirementsHumidity level Dust and pollutionMetallic particulate contamination Electrostatic discharge prevention Acoustic noise specificationAshrae Recommended operating environmentSpace requirements Airflow requirementsBlanking panels HP Rack Airflow Optimization KitOperational space requirements Delivery space requirementsEquipment clearance and floor loading Floor plan grid HP BladeSystem enclosure environmental specifications Rack and accessory footprintsFront door clearance Environmental requirements Environmental requirements Best practices for deployment in rows Third-party racks Rack placement and arrangement for proper airflowRack tie-down option kit Power requirements Power requirements and considerationsElectrical factors Power consumption Electrical load requirements circuit breaker sizing Power considerations Power qualityFactors affecting power quality Power system protectionPower redundancy Power optionsWire selection Non-redundant powerDistribution hardware Line voltage selectionGrounding systems Grounding requirementsRaceway systems electrical conduits Lahj Building distributionPower panel ground Power distribution safety grounding LahjComputer safety ground Dual power source groundingRaised floor high-frequency noise grounding Cabinet performance grounding high frequency groundWiring connections System installation guidelinesEquipment grounding implementation details Dynamic Power Capping Power configurationHP BladeSystem enclosure single-phase power configuration Data communications cablesPower requirements and considerations Power requirements and considerations Power requirements and considerations C7000 PDU example PDU installationC3000 PDU example HP BladeSystem c7000 Enclosure three-phase AC configuration HP BladeSystem c7000 Enclosure DC configuration HP BladeSystem enclosure DC power configurationSingle-phase HP 2250W Power Supply specification Power supply specificationsHP BladeSystem c3000 Enclosure DC configuation Specification Value Specification Value DC power supply specification Enclosure specifications Hardware specifications and requirementsHP BladeSystem c7000 Enclosure specifications HP BladeSystem c3000 Enclosure specificationsRack requirements HP 10000 G2 rack specificationsRack-free environment requirements Example configurations Configuration scenariosExample minimum configuration Example typical configurationExample maximum configuration Estimating power and cooling Estimating total weight Preparing for installation Preparing for installation Additional rack considerations General component placement guidelinesRack configuration software Sample checklists Sample installation scheduleIs there a completed floor plan? Delivery survey Page Conversion factors Conversion factors and formulasFormulas Before you contact HP Technical supportHP contact information Acronyms and abbreviations UPS Glossary Apparent powerKVA Index Site planning assistance from HP