Samsung AF0AKV3SAEENSG manual Gas leak test and vacuum drying

Page 65

3Install a green / yellow grounding wire:

––Please refer to the “Wiring work” for the specification of grounding wire.

––When the grounding wire is too short,extend the grounding wire but bind the connection part with insulation tepe.Extend the ground lead if too short and use the heat-insulated tape to secure the connection part.

(Do not bury the connection)

––Secure the grounding wire in position with staples.

CAUTION

When the grounding rod is installed in a place where many people pass by,you must fix it firmly.

4Carefully check the installation,by measuring the grounding resistance with a ground resistance tester.

––If the resistance is above required level,drive the grounding rod deeper into the ground or increase the number of grounding rods.

5Connect the grounding wire to the electrical component box inside of the outdoor unit.

Gas leak tests on the outdoor unit is done initially from the factory, but you must test for gas leakage after the installation.

Gas leak test and vacuum drying

Gas leak tests on the outdoor unit is done initially from the factory, but you must test for gas leakage after the installation.

1Purge the pipe and run vacuum test. (Pressure should not increase for a minute.)

2Insert the nitrogen gas so that pressure reaches minimum 2kg/cm2.

3Use soap water to check the leakage on the connection part.

4For final vacuum test, leave the outdoor unit for 24 hours under pressure of 28kg/cm2 and check for any signs of pressure decrease.

5Discharge the nitrogen gas.

6Keep the outdoor unit in vacuum status.

7If length of the pipe exceeds the standard length, charge additional refrigerant.

8Open the outdoor unit valve and circulate the refrigerant to the indoor unit so that pressure of the entire pipe becomes even.

INSTALLATION PARTS

English 65

Image 65
Contents Air conditioner Contents Safety precautions For Installation Using Parts For Power Supply Using Parts Safety precautions Using Parts For Cleaning Checking the auxiliary power switch Using outdoor unitOperational temperature and humidity range Checking before useTo open the panel Viewing the partsMain parts Control panel and the display Locking the control panelUsing the air conditioner with the control panel Remote controller button Checking the remote controllerInserting the batteries Remote controller displayStoring the remote controller Battery changing timeCool Basic operationAuto DryAdjusting the air flow direction Using the Turbo function Setting the On timer Timer functionSetting the Off timer Cleaning the outdoor unit heat exchanger Cleaning and maintaining the air conditionerCleaning the indoor unit Cleaning the air filter Maintaining the air conditioner Periodical checks Problem Solution TroubleshootingTroubleshooting General information Power supply line, fuse or circuit breaker Installing the unitInstallation Parts Accessory parts list Moving the outdoor unit Preparation for installationIndoor  outdoor unit type and combination Indoor unit Deciding on where to install the productOutdoor unit Deciding on where to install the product Space requirements Installation location 2000 Or more 300 or More 1500 or Or 600 or more more Or more Drilling a hole in the wall Pipe length between the indoor and the outdoor unitLess than 30m Installing Outdoor unit Installing indoor unitBase ground contruction Installation Parts Installation Parts Refrigerant piping work Connecting the pipesFix the pipe on Indoor Temper grade and minimum thickness of the refrigerant pipe Pipe connectionSelecting refrigerant pipe Storing refrigerant pipe Cutting or flaring the pipes Direction of the pipe when brazingTightening flare connection part Pipe bending Connecting the drain hoseInsulating refrigerant pipe Selecting the insulator of the refrigerant pipeAllowable refrigerant pipe length Refrigerant chargingHow to add refrigerant Electrical work Wiring workPower supply and wire specification Phase 4 wires Power wiring diagramEarth Connecting power and communication cableSelecting solderless ring terminal Connecting the power terminal Connect the ring terminal Fixing the power cableGrounding work Installing grounding wire Wiring work Gas leak test and vacuum drying Check lists after completing the installation Testing operations SEG2 SEG3 SEG4 On on Check electrical connection and setting E441 IPM Installationparts How to connect your extended power cables Installation Parts Packing and unpacking guide Packing the indoor unit Unpacking the indoor unitPacking the outdoor unit Unpacking the outdoor unitCooling Questions or COMMENTS?