Samsung AF0AKV3SAEENSG manual Wiring work, Electrical work

Page 56

INSTALLATION PARTS

Wiring work

Electrical work

Wiring work should be performed in accordance with related laws such as technical specification on electric installation or installation guide.

Copper cable should be used for wiring work and all the wirings or parts should be rated products.

Wiring work should be performed by a company certified by an electric power company.

Refer to the circuit diagram attached to the outdoor unit for detailed wiring work.

Wiring work should be performed after disconnecting main circuit breaker and Y-joint switch.

You must perform ground working 3. (Grounding resistance value should be less than 100Ω.) When ELB is installed, protective grounding resistance value can be applied. (When the ELB is 100mA, 0.1sec, protective grounding resistance value should be less than 250Ω at a place where electric danger is high and should be less than 500Ω at other places. )

Do not connect the ground wire to the gas pipe, water pipe, lightning rod, or telephone.

––Gas pipe: If the gas leaks, explosion or ignition may occur.

––Water pipe: If rigid vinyl pipe is used, there will be no grounding effect.

––Ground wire of telephone and lightning rod: The electric potential of ground wire may rise abnormally when lightening strikes.

The ELB for ground-fault protection should be combined with MCCB or fuse equipped load switch. In this case, you should use the one that has at least the same or larger fuse capacity or the rated current of MCCB.

Use the wires that comply with regulated specification and firmly connect to the terminal board. Then tighten it with the provided screws so that the terminal board (connecting cable locally procured, grounding terminal) cannot be moved by external force.

When connecting outdoor unit main power, be aware of the connection order for 3 phase (R, S, T, N).

Standard power cable length should be below 50m.

––If the length has to be over 50m, contact service center.

Fix a cable tube using a CD connector (wire conduit) and bushing at the knock-out hole of the outdoor unit.

56English

Image 56
Contents Air conditioner Contents Safety precautions For Installation Using Parts For Power Supply Using Parts Safety precautions Using Parts For Cleaning Using outdoor unit Checking the auxiliary power switchOperational temperature and humidity range Checking before useTo open the panel Viewing the partsMain parts Locking the control panel Control panel and the displayUsing the air conditioner with the control panel Checking the remote controller Remote controller buttonRemote controller display Inserting the batteriesBattery changing time Storing the remote controllerBasic operation CoolAuto DryAdjusting the air flow direction Using the Turbo function Timer function Setting the On timerSetting the Off timer Cleaning the outdoor unit heat exchanger Cleaning and maintaining the air conditionerCleaning the indoor unit Cleaning the air filter Maintaining the air conditioner Periodical checks Troubleshooting Problem SolutionTroubleshooting General information Installing the unit Power supply line, fuse or circuit breakerInstallation Parts Accessory parts list Moving the outdoor unit Preparation for installationIndoor  outdoor unit type and combination Deciding on where to install the product Indoor unitOutdoor unit Deciding on where to install the product Space requirements Installation location 2000 Or more 300 or More 1500 or Or 600 or more more Or more Drilling a hole in the wall Pipe length between the indoor and the outdoor unitLess than 30m Installing indoor unit Installing Outdoor unitBase ground contruction Installation Parts Installation Parts Connecting the pipes Refrigerant piping workFix the pipe on Indoor Temper grade and minimum thickness of the refrigerant pipe Pipe connectionSelecting refrigerant pipe Storing refrigerant pipe Direction of the pipe when brazing Cutting or flaring the pipesTightening flare connection part Connecting the drain hose Pipe bendingSelecting the insulator of the refrigerant pipe Insulating refrigerant pipeRefrigerant charging Allowable refrigerant pipe lengthHow to add refrigerant Wiring work Electrical workPower supply and wire specification Power wiring diagram Phase 4 wiresConnecting power and communication cable EarthSelecting solderless ring terminal Connecting the power terminal Fixing the power cable Connect the ring terminalGrounding work Installing grounding wire Wiring work Gas leak test and vacuum drying Check lists after completing the installation Testing operations SEG2 SEG3 SEG4 On on Check electrical connection and setting E441 IPM Installationparts How to connect your extended power cables Installation Parts Packing and unpacking guide Unpacking the indoor unit Packing the indoor unitUnpacking the outdoor unit Packing the outdoor unitCooling Questions or COMMENTS?