Samsung AF0AKV3SAEENSG manual Periodical checks

Page 26

USING PARTS

Cleaning and maintaining the air conditioner

Periodical checks

Refer to the following chart to maintain the air conditioner properly.

Type

Description

Every 2

Every 3

Every 4

Once a

weeks

months

months

year

 

 

 

Clean the air filter (1)

 

 

 

Indoor

Clean the condensate drain pan (2)

 

 

 

unit

Thoroughly clean the heat exchanger (2)

 

 

 

 

Clean the condensate drain pipe (2)

 

 

 

 

Clean the heat exchanger on the outside

 

 

 

 

of the unit (2)

 

 

 

 

 

 

 

 

 

Clean the heat exchanger on the inside

 

 

 

 

of the unit (2)

 

 

 

 

 

 

 

 

 

Clean the electric components with jets

 

 

 

Outdoor

of air (2)

 

 

 

 

 

 

 

unit

Verify that all the electric components

 

 

 

 

are firmly tightened (2)

 

 

 

 

 

 

 

 

 

Clean the fan (2)

 

 

 

 

Verify that all the fan assembly is firmly

 

 

 

 

tightened (2)

 

 

 

 

 

 

 

 

 

Clean the condensate drain pan (2)

 

 

 

: This check mark requires checking the indoor/outdoor unit periodically, following to the description to maintain the air conditioner properly.

NOTE

The checks and maintenance operations described are essential to guarantee the efficiency of the air conditioner. The frequency of these operations varies according to the characteristics of the area, the amount of dust, etc.

––The described operations should be performed more frequently if the area of installation is very dusty.

––These operations must always be performed by qualified personnel. For more detailed information, see the Installation part.

26English

Image 26
Contents Air conditioner Contents Safety precautions For Installation Using Parts For Power Supply Using Parts Safety precautions Using Parts For Cleaning Operational temperature and humidity range Using outdoor unitChecking the auxiliary power switch Checking before useTo open the panel Viewing the partsMain parts Locking the control panel Control panel and the displayUsing the air conditioner with the control panel Checking the remote controller Remote controller buttonRemote controller display Inserting the batteriesBattery changing time Storing the remote controllerAuto Basic operationCool DryAdjusting the air flow direction Using the Turbo function Timer function Setting the On timerSetting the Off timer Cleaning the outdoor unit heat exchanger Cleaning and maintaining the air conditionerCleaning the indoor unit Cleaning the air filter Maintaining the air conditioner Periodical checks Troubleshooting Problem SolutionTroubleshooting General information Installing the unit Power supply line, fuse or circuit breakerInstallation Parts Accessory parts list Moving the outdoor unit Preparation for installationIndoor  outdoor unit type and combination Deciding on where to install the product Indoor unitOutdoor unit Deciding on where to install the product Space requirements Installation location 2000 Or more 300 or More 1500 or Or 600 or more more Or more Drilling a hole in the wall Pipe length between the indoor and the outdoor unitLess than 30m Installing indoor unit Installing Outdoor unitBase ground contruction Installation Parts Installation Parts Connecting the pipes Refrigerant piping workFix the pipe on Indoor Temper grade and minimum thickness of the refrigerant pipe Pipe connectionSelecting refrigerant pipe Storing refrigerant pipe Direction of the pipe when brazing Cutting or flaring the pipesTightening flare connection part Connecting the drain hose Pipe bendingSelecting the insulator of the refrigerant pipe Insulating refrigerant pipeRefrigerant charging Allowable refrigerant pipe lengthHow to add refrigerant Wiring work Electrical workPower supply and wire specification Power wiring diagram Phase 4 wiresConnecting power and communication cable EarthSelecting solderless ring terminal Connecting the power terminal Fixing the power cable Connect the ring terminalGrounding work Installing grounding wire Wiring work Gas leak test and vacuum drying Check lists after completing the installation Testing operations SEG2 SEG3 SEG4 On on Check electrical connection and setting E441 IPM Installationparts How to connect your extended power cables Installation Parts Packing and unpacking guide Unpacking the indoor unit Packing the indoor unitUnpacking the outdoor unit Packing the outdoor unitCooling Questions or COMMENTS?