8Install a square pad(t=20mm or more) to prevent vibration from the outdoor unit onto the base ground. Place the outdoor unit on the H beam and fix it with the bolt, nut and washer. (Fix with M10 basic anchor bolt, nut and washer.)
Outdoor unit | Unit: mm |
|
Anchor bolt | 20mm | |
| ||
| Square pad | |
Nut, Spring wahser |
| |
75mm or | ||
A | ||
more | ||
| ||
| A+10~20mm or more |
Base ground contruction
| 150 mm | Install the outdoor unit horizontally | |||
Drain hole | on the ground |
| |||
or more | 150 mm or more | ||||
|
|
| |||
(when Installing on the ground) | (when Installing on the roof) |
•The outdoor unit should be supported within the range of measurement below for base ground work.
INSTALLATION
Anchor bolt position
460 | 464 |
| 620 |
| 940 |
Unit: mm
520