Excalibur electronic P95-NG3, P95-LP3 Horizontal Venting with Two 2 90o Elbows, Option + H1

Page 16

INSTALLATION

Horizontal Venting with Two (2) 90o Elbows

One 90o elbow = Two 45o elbows.

Option

 

V

H + H1

With

these options,

A)

0'

Min.

2' Max.

maximum total pipe length

 

 

 

 

is 30 feet with minimum

B)

1'

Min.

3' Max.

 

 

 

 

of 6

feet total vertical

C)

2'

Min.

4' Max.

and maximum 8 feet total

D)

3'

Min.

5' Max.

horizontal.

E)

4'

Min.

6' Max.

Please note minimum 1

F)

5'

Min.

7' Max.

 

 

 

 

foot between 90o elbows

G)

6' Min.

8' Max.

is required.

 

 

 

 

 

 

 

 

 

 

Horizontal Venting with Three (3) 90o Elbows

One 90o elbow = Two 45o elbows.

Option V

H

V + V1 H + H1

A)0' Min. 1' Max. 1' Min. 2' Max.

B)1' Min. 2' Max. 3' Min. 3' Max.

C)2' Min. 2' Max. 5' Min. 4' Max.

D)3' Min. 2' Max. 7' Min. 5' Max.

E)4' Min. 3 Max. 9' Min. 6' Max.

F)5' Min. 4' Max. 10' Min. 7' Max.

G)6' Min. 5' Max. 11' Min. 8' Max.

H)7' Min. 6' Max. 12' Min. 9' Max.

With these options, max. total pipe length is 30 feet with min. of 12 feet total vertical and max. 9 feet total horizontal.

Please note min. 1 foot between 90o elbows is required.

16

Excalibur® P95-3 Zero Clearance Direct Vent Gas Fireplace

Image 16
Contents P95-3 Zero Clearance Direct Vent Gas Fireplace 07/17/06Congratulations To the New OwnerTable of Contents Safety Label Copy of Safety Decal for P95-3Requirements For the State of Massachusetts onlyInstallation General Safety InformationInstallation Checklist Important Message Save These InstructionsLocating Your GAS Fireplace Manufactured Mobile Home Additional RequirementsOptional Heatwave Duct System KIT Optional Heat Release KITFraming Dimensions Combustible MantelsFraming Finishing Unit Base STAND-OFFSFacing Requirement Hearth RequirementsFacing Over 1 25mm Thick Floor Mounted Fireplaces Raised FireplacesUnit Assembly Prior to Installation Top Standoff AssemblyVenting Introduction Side Nailing StripsVenting FPI Direct Vent System Flex Horizontal Terminations OnlyExterior Vent Termination Locations Flat Wall Installation Wall Thickness Vent Length Required Corner InstallationSimpson DURA-VENT Venting Alternate Horizontal Termination CapDescription Simpson DURA-VENT Venting Components ListParts not supplied by Dura-Vent Venting Arrangements Horizontal Terminations FPI Direct Vent System FlexHorizontal Venting with Two 2 90o Elbows Horizontal Venting with Three 3 90o ElbowsOption + H1 Option + V1 H + H1Vertical Venting with Three 3 90o Elbows Vertical Venting with Two 2 90o ElbowsOption Venting Arrangements Vertical Terminations Simpson DURA-VENT Direct Vent GS SystemInstallation Below Grade Installation Snorkel TerminationsVertical Termination Continue to assemble pipe lengthsInstallation Procedures Offset ChartFor FPI Direct Vent System Flex GS 8 Nominal Diameter ID OffsetPilot Adjustment GAS Line InstallationGAS Pipe Pressure Testing High ElevationInstallation of LPG Conversion Kit Installation of the DC Sparker Heat Shield LOG SET Installation Optional Brick PanelsPicture below is a view from the back of the burner Glass Door Installation Optional Screen DoorsFront Facade Tab ScrewAccent KIT Installation Single Door AccentsThermostat Wire Table Wall ThermostatWiring Diagrams Do not cut the ground terminal off under any circumstancesFor Propane Units and Units Equipped with DC Spark Boxes Operating Instructions Normal Operating Sounds of GAS Appliances Copy of the Lighting Plate InstructionsMaintenance FAN Maintenance To Install the FansShut the power off To Remove the FansRemoving Valve Installing ValveBrick panel is very fragile handle with care Parts List P95-3 Main AssemblyParts List P95-3 Burner Assembly & LOG SET P95-3 Flush Front Accessories DescriptionWarranty Warranty Limited LifetimeInstaller Please complete the following information