INSTALLATION

the vertical height must be increased. A poor draft, or down drafting can result from high wind conditions near big trees or adjoining roof lines, in these cases, increasing the vent height may solve the problem.

7)Ensure vent is vertical and secure the base of the fl ashing to the roof with roofi ng rails, slide storm collar over the pipe section and seal with a mastic.

8)Install the vertical termination cap by twist- locking it.

Note: Any closets or storage spaces, which the vent passes through must be enclosed.

Offset Chart

GS 8" Nominal Diameter ID

Offset

Pipe Length

 

Height

5-11/16"

0"

 

 

 

15-5/16"

 

 

 

 

 

8-13/16"

6"

 

 

15-7/16"

 

 

 

 

 

 

10-15/16"

9"

 

 

 

20-9/16"

13"

12"

 

 

22-11/16"

21-7/16"

24"

 

 

31-1/16"

 

 

 

 

 

29-13/16"

36"

 

 

37-7/16"

38-1/4"

48"

 

 

47-7/8"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

INSTALLATION

PROCEDURES

for FPI Direct Vent

System (Flex)

1)Locate the unit in the framing, rough in the gas (preferably on the right side of the unit) and the electrical (Junction block is on the left side) on the left. Locate the centerline of the termination and mark wall accordingly. Cut a 11"(279mm) hole in the wall (inside dimension).

Note: A 3-1/2"(76mm) clearance around the liner must be maintained except that only a 1" (25mm) clearance is needed at the termination end. We recommend framing a 11"(279mm) x 11"(279mm)(insidedimensions)hole togivestructuralrigidityformounting the termination.

Note: To make the installation more aesthetically p l e a s i n g , w e recommend framing outasquaretomount the terminal to.

Note: If installing termination on a siding covered wall, furring strips must be used to ensure that the termination is not recessed into the siding.

2)Level the fireplace and fasten it to the framing using nails or screws through the nailing strips.

3)Assemble the vent assembly by applying Mill Pac to the 5"(127mm) inner collar of the termination and slipping the 5"(127mm) liner over it at least 1-3/8" (35mm). Fasten with the 3 screws (drilling pilot holes will make this easier). Apply Mill Pac or high temperature silicone to the 8"(203mm) fl ex pipe and slip it over the 8"(203mm) outer collar of the vent terminal at least 1-3/8"(35mm) and fasten with the 3 screws.

NOTE: Horizontal sections must be supported at intervals not exceeding 3 feet (0.9 meter). (Flame picture and performance will be affected by sags in the liner).

4)Separate the 2 halves of the wall thimble and securely fasten the one with the tabs to the outside wall making sure that the tabs are on top and bottom. Fasten the other thimble half to the inside wall. The thimble halves slip inside each other and can be adjusted for 2 x 4 or 2 x 6 walls. The liners must slip over the collars a minimum of 1-3/8".

5)Slip the assembled liner and termination assembly through the thimble making sure the termination cap faces up (there are markings on the cap that show which way is up). This will position the termination cap with proper down slope for draining water. Fasten the cap to the outer wall with the 4 supplied screws.

6)Pull the centre 5"(127mm) liner and outer 8"(203mm) liner out enough to slip over the fl ue collars of the fi replace. (You may wish to cut the liner shorter to make it more workable.) Do not bend liner more than 90o.

7)Apply Mill Pac over the fi replace inner collar and slip the 5"(127mm) liner down over it and attach with 3 supplied screws.

8)Do the same with the 8"(203mm) liner.

9)Apply a bead of silicone between the thimble and termination and around the outer edge of the terminal at the wall in order to keep the water out.

IMPORTANT: Do not locate termination hood where excessive snow or ice buildup may occur. Be sure to check vent termination area after snow falls, and clear to prevent accidental blockage of venting system. When using snow blowers, make sure snow is not directed towards vent termination area.

22

Excalibur® P95-3 Zero Clearance Direct Vent Gas Fireplace

Image 22
Contents P95-3 Zero Clearance Direct Vent Gas Fireplace 07/17/06Congratulations To the New OwnerTable of Contents Safety Label Copy of Safety Decal for P95-3Requirements For the State of Massachusetts onlyInstallation Checklist InstallationGeneral Safety Information Important Message Save These InstructionsOptional Heatwave Duct System KIT Locating Your GAS FireplaceManufactured Mobile Home Additional Requirements Optional Heat Release KITFraming Finishing Framing DimensionsCombustible Mantels Unit Base STAND-OFFSFacing Over 1 25mm Thick Facing RequirementHearth Requirements Floor Mounted Fireplaces Raised FireplacesVenting Introduction Unit Assembly Prior to InstallationTop Standoff Assembly Side Nailing StripsVenting FPI Direct Vent System Flex Horizontal Terminations OnlyExterior Vent Termination Locations Simpson DURA-VENT Venting Flat Wall Installation Wall Thickness Vent Length RequiredCorner Installation Alternate Horizontal Termination CapDescription Simpson DURA-VENT Venting Components ListParts not supplied by Dura-Vent Venting Arrangements Horizontal Terminations FPI Direct Vent System FlexOption + H1 Horizontal Venting with Two 2 90o ElbowsHorizontal Venting with Three 3 90o Elbows Option + V1 H + H1Vertical Venting with Three 3 90o Elbows Vertical Venting with Two 2 90o ElbowsOption Venting Arrangements Vertical Terminations Simpson DURA-VENT Direct Vent GS SystemInstallation Below Grade Installation Snorkel TerminationsVertical Termination Continue to assemble pipe lengthsFor FPI Direct Vent System Flex Installation ProceduresOffset Chart GS 8 Nominal Diameter ID OffsetGAS Pipe Pressure Testing Pilot AdjustmentGAS Line Installation High ElevationInstallation of LPG Conversion Kit Installation of the DC Sparker Heat Shield LOG SET Installation Optional Brick PanelsPicture below is a view from the back of the burner Front Facade Glass Door InstallationOptional Screen Doors Tab ScrewAccent KIT Installation Single Door AccentsThermostat Wire Table Wall ThermostatWiring Diagrams Do not cut the ground terminal off under any circumstancesFor Propane Units and Units Equipped with DC Spark Boxes Operating Instructions Normal Operating Sounds of GAS Appliances Copy of the Lighting Plate InstructionsMaintenance Shut the power off FAN MaintenanceTo Install the Fans To Remove the FansRemoving Valve Installing ValveBrick panel is very fragile handle with care Parts List P95-3 Main AssemblyParts List P95-3 Burner Assembly & LOG SET P95-3 Flush Front Accessories DescriptionWarranty Warranty Limited LifetimeInstaller Please complete the following information