Excalibur electronic P95-NG3, P95-LP3 installation manual Removing Valve, Installing Valve

Page 38

MAINTENANCE

REMOVING VALVE

1)Shut the power off.

2)Open the bottom louver door. Loosen the 2 screws holding the Burner ON/OFF switch and bracket to the bottom louver and lift the assembly out.

3)Remove the facade if installed.

4)Remove the glass door.

5)Remove the logs.

6)Remove the burner/grate assembly, fi rst by removing the 2 screws, 1 on each side of the grill, then lift out the grill.

9)Remove the front bottom brick panel by sliding it out. Then remove the back bottom brickpanelbytilting itslightlyupandthenout.

The brick panel is very fragile - handle with care.

10)Disconnect the inlet gas line. See dia. 2.

11)Disconnect the 2 TP wires and the 2 TH wires from the valve.

12)Remove the 12 screws securing the valve tray assembly in place and then lift the entire assembly out.

Hint:

If you are using black pipe, ensure

 

that there is a union by the valve,

 

otherwise removal will be almost

 

impossible.

 

 

INSTALLING VALVE

1)Attach the valve to the valve bracket with the 4 (m5x8 metric) screws provided.

2)Reconnect the "gas out" fl are fi tting with an 11/16" wrench.

3)Reconnect the "gas out" fl are nut with a 13/16" wrench.

4)Install piezo ignitor push button assembly and reconnect wire.

5)Reconnect the quick drop out thermocouple nut with a 9mm wrench.

6)Reconnect the pilot tube nut with a 7/16" wrench.

Remove screw

7)Remove the 2 screws, 1 on each side of the burner. Slide the burner to the left and then lift out.

Remove screw

Slide the burner to the left and lift out.

8)Remove the rear log stand by removing the 2 screws.

Rear Log Stand

Valve Tray Assembly

13)Undo the pilot tube from the valve with a 7/16" wrench.

14)Undo the quick drop out thermocouple nut on the valve with a 9mm (metric) wrench.

15)Remove the Piezo igniter wire and push button assembly.

16)Undo the "gas out" fl are nut with a 13/16" wrench.

17)Undo the "gas out" fl are fi tting with an 11/16" wrench.

18)Remove the 4 Phillips head screws from the sides of the valve bracket and remove valve.

7) Scrape off the old gasket from the floor of the

fi rebox and from the valve tray assembly.

8)Install a new gasket and reinstall the valve tray assembly.

Note: Failure to install a new gasket may severely affect the appliance performance.

9)Reinstall the 10 hold down screws.

10)Hook up the 2 TP and 2 TH wires to the appropriate connections on the valve.

11)Reinstall the bottom brick panel, then screw the 2 screws & sleeves through the brick panel to the fi rebox base (reversing step 8) leaving them about 1/4" (6mm) above the brick panel. Reinstall the rear log stand.

12)Install Burner/grate assembly

13)Hook up the gas line and check for gas leaks with a soap and water solution or a gas leak detector. (Do not use open fl ame for leak testing.)

14)Fire up the unit temporarily

15)Check the manifold pressure.

16)Reinstall the logs and brick panels as needed.

17)Reinstall the glass door and the facade.

18)Fire up the unit again and check for proper fl ame appearance and glow on logs.

38

Excalibur® P95-3 Zero Clearance Direct Vent Gas Fireplace

Image 38
Contents P95-3 Zero Clearance Direct Vent Gas Fireplace 07/17/06Congratulations To the New OwnerTable of Contents Safety Label Copy of Safety Decal for P95-3Requirements For the State of Massachusetts onlyInstallation Checklist InstallationGeneral Safety Information Important Message Save These InstructionsOptional Heatwave Duct System KIT Locating Your GAS FireplaceManufactured Mobile Home Additional Requirements Optional Heat Release KITFraming Finishing Framing DimensionsCombustible Mantels Unit Base STAND-OFFSFacing Over 1 25mm Thick Facing RequirementHearth Requirements Floor Mounted Fireplaces Raised FireplacesVenting Introduction Unit Assembly Prior to InstallationTop Standoff Assembly Side Nailing StripsVenting FPI Direct Vent System Flex Horizontal Terminations OnlyExterior Vent Termination Locations Simpson DURA-VENT Venting Flat Wall Installation Wall Thickness Vent Length RequiredCorner Installation Alternate Horizontal Termination CapParts not supplied by Dura-Vent Simpson DURA-VENT Venting Components ListDescription Venting Arrangements Horizontal Terminations FPI Direct Vent System FlexOption + H1 Horizontal Venting with Two 2 90o ElbowsHorizontal Venting with Three 3 90o Elbows Option + V1 H + H1Option Vertical Venting with Two 2 90o ElbowsVertical Venting with Three 3 90o Elbows Venting Arrangements Vertical Terminations Simpson DURA-VENT Direct Vent GS SystemInstallation Below Grade Installation Snorkel TerminationsVertical Termination Continue to assemble pipe lengthsFor FPI Direct Vent System Flex Installation ProceduresOffset Chart GS 8 Nominal Diameter ID OffsetGAS Pipe Pressure Testing Pilot AdjustmentGAS Line Installation High ElevationInstallation of LPG Conversion Kit Installation of the DC Sparker Heat Shield LOG SET Installation Optional Brick PanelsPicture below is a view from the back of the burner Front Facade Glass Door InstallationOptional Screen Doors Tab ScrewAccent KIT Installation Single Door AccentsThermostat Wire Table Wall ThermostatWiring Diagrams Do not cut the ground terminal off under any circumstancesFor Propane Units and Units Equipped with DC Spark Boxes Operating Instructions Normal Operating Sounds of GAS Appliances Copy of the Lighting Plate InstructionsMaintenance Shut the power off FAN MaintenanceTo Install the Fans To Remove the FansBrick panel is very fragile handle with care Installing ValveRemoving Valve Parts List P95-3 Main AssemblyParts List P95-3 Burner Assembly & LOG SET P95-3 Flush Front Accessories DescriptionWarranty Warranty Limited LifetimeInstaller Please complete the following information