Potthof & Co 33kw System Filling and Pressurising Fig, Expansion Vessel Central Heating only

Page 13

Stop

Double

Check

Valve

Valve

 

DHW

Temporary

Hose

Mains

 

Inlet

 

Fig. 4

Stop

Valve

CH Return

6.0System Details

6.5System Filling and Pressurising (Fig. 4)

1.A filling point connection on the central heating return pipework must be provided to facilitate initial filling and pressurising and also any subsequent water loss replacement/refilling.

A filling loop & instructions are provided with the boiler

2.The filling method adopted must be in accordance with all relevant water supply regulations and use approved equipment.

3.Your attention is drawn to:

for GB: Guidance G24.2 and recommendation R24.2 of the Water Regulations Guide.

for IE: the current edition of I.S. 813 “Domestic Gas Installations”.

4.The sealed primary circuits may be filled or replenished by means of a temporary connection between the circuit and a supply pipe, provided a ‘Listed’ double check valve or some other no less effective backflow prevention device is permanently connected at the inlet to the circuit and the temporary connection is removed after use.

6.6Expansion Vessel (Central Heating only)

Filling Loop

Fig. 5

Fig. 6

Pressure Relief Valve

Discharge Pipe

1.The appliance expansion vessel is pre-charged to 0.5 bar. Therefore, the minimum cold fill pressure is 0.5 bar. The vessel is suitable for correct operation for system capacities up to 125 litres (24, 28 models) 155 litres (33 models). For greater system capacities an additional expansion vessel must be fitted. For GB refer to BS 7074 Pt 1. For IE, the current edition of I.S. 813 “Domestic Gas Installations”.

6.7Safety Pressure Relief Valve (Fig. 6)

1.The pressure relief valve is set at 3 bar, therefore all pipework, fittings, etc. should be suitable for pressures in excess of 3 bar and temperature in excess of 100°C.

2.The pressure relief discharge pipe should be not less than 15mm dia, run continuously downward, and discharge outside the building, preferably over a drain. It should be routed in such a manner that no hazard occurs to occupants or causes damage to wiring or electrical components. The end of the pipe should terminate facing down and towards the wall.

3.The discharge must not be above a window, entrance or other public access. Consideration must be given to the possibility that boiling water/steam could discharge from the pipe.

4.A remote relief valve kit is available to enable the boiler to be installed in cellars or similar locations below outside ground level (kit no. 5121379).

© Baxi Heating UK Ltd 2012

13

Image 13
Contents Installation & Service Instructions Benchmark Scheme Natural GasScheme Members only Installer Notification GuidelinesLegislation Important Installation, Commissioning, Service & RepairCodes of Practice refer to the most recent version General Safe Manual HandlingPreparation TechniqueContents Introduction Contents of PackDescription Layout General LayoutExpansion Vessel Automatic Air Vent Circulation Pump Drain Off PointDomestic Hot Water Mode Fig Central Heating Mode FigFrost Protection Mode Appliance OperationGold Combi 24, 28 & 33 HE a Technical DataDimensions and Fixings Information System DetailsCentral Heating Circuit BypassSystem Filling and Pressurising Fig Safety Pressure Relief Valve FigExpansion Vessel Central Heating only Showers Domestic Hot Water Circuit FigHard Water Areas Location Site RequirementsClearances Figs At leastVentilation of Compartments Site RequirementGas Supply Electrical SupplyPipe run Minimum Fall PerPer Metre Run50mm per Minimum Fall500mm min Minimum fall RunFlue Plume Displacement KitBelow windows or openings on pitched roofs 2000 Likely flue positions requiring a flue terminal guardTotal equivalent length = +B+C+2x90Bends Flue OptionsTotal Equivalent Length = +B+C+1x90Bend Key Accessory Size Code No Flue AccessoriesTelescopic Flue inc. elbow Twin Flue Connection Twin Flue Duct AdaptorAir Duct Connection Flue Duct Connection Boiler Adaptor For Roof Terminals Flue DimensionsFlue Trim Terminal Guard FigPlume Displacement Kit Fig Plume DisplacementDetermining Permissible Lengths 28/33Example ElbowGeneral Fitting Notes 50mm30mm 60Ø extension piece. It must be secured using two Elbow to allow the flue to be installed as shownUsing a suitable bit e.g mm, drill through Extension and outlet. Secure using two of the screwsUnpacking & Initial Preparation InstallationFlushing After considering the site requirementsFitting the Filling Loop Kit Fitting The Boiler Fitting the Safety Pressure Relief Discharge Pipe FigCondensate Drain see section Tighten all the connectionsWall Thickness Flue Elbow Fitting The FlueEnsure Elbow is fully engaged into Boiler Adaptor Wall Thickness Waste Flue25mm Extension Cut End Inner Flue Support BracketEnsure Extension is fully engaged into Boiler Adaptor Preliminary Electrical Checks Making The Electrical ConnectionsTerminal Block Cover Cable Clamp Commissioning Selector Switch DisplayCommissioning the Boiler Screw Pump Automatic Air VentTemperature Control Gas Pressure Test Point Gas Valve Temperature Control Selector Switch DisplayCheck the Operational Working Gas Inlet Pressure It is necessary to set the boiler to ‘Calibration Mode’Setting the Timer Completion CompletionCase Front Panel Facia Panel 13 .1 Annual Servicing ServicingAnnual Servicing Inspection 10 ±1 Electrode PositionIgniter Fig Changing ComponentsSpark and Sensing Electrodes Fig Venturi Fig Fan FigInjector Fig Gasket Venturi Injector Cover Gas Inlet Pipe Fan CollectorInsulation Fig Burner FigExtension Piece Safety Thermostat Fig Central Heating Temperature Sensor NTC FigDHW Temperature Sensor NTC Fig Flue/Heat Exchanger Thermostat Sensor FigPump Complete Fig Pump Head Only FigAutomatic Air Vent Fig Hall Effect Sensor Fig Pressure Gauge FigsPressure Relief Valve Fig Plate Heat Exchanger Fig Diverter Valve Motor Unit & Assembly Fig14.22 P.C.B. Fig Selector Switch FigExpansion Vessel Fig Gas Valve FigSetting the Gas Valve CO2 check Setting the Gas ValveFlue Adaptor Test Point Plug Analyser Probe CO2 should be 8.4% ± Reduce CO2Electrical Illustrated Wiring DiagramShort Parts List Short Parts List426 315316 311 404419 422 400 415Initial Fault Finding Checks Fault FindingError Codes Go to section ‘A’ Turn the selector switch to Error 133 flashingReset position for 5 seconds Pump runsTurn Domestic Hot Water Error 133 flashing Go to section ‘I’Open DHW tap fully Close DHW tapSwitch terminal PCB X3 connector terminals 3Fan jammed or faulty winding Replace PCB Replace waterReplace sensor or PCB E28 Check wiring Viewing WindowGas at burner Replace gas valveReplace PCB Is there 230V at Replace safety thermostatReplace sensor Pages for Notes Pages for Notes GAS Boiler System Commissioning Checklist Service Record Potterton