Potthof & Co 28kw Flue, Below windows or openings on pitched roofs 2000, Plume Displacement Kit

Page 20

 

Terminal Position with Minimum Distance (Fig. 18)

(mm)

A1

Directly below an opening, air brick, opening

 

B1

windows, etc.

300

Above an opening, air brick, opening window etc.

300

C1

Horizontally to an opening, air brick, opening window etc.

300

D2

Below gutters, soil pipes or drain pipes.

25 (75)

E2

Below eaves.

25 (200)

F2

Below balconies or car port roof.

25 (200)

G2

From a vertical drain pipe or soil pipe.

25 (150)

H2

From an internal or external corner.

25 (300)

I

Above ground, roof or balcony level.

300

J

From a surface or boundary line facing a terminal.

600

K

From a terminal facing a terminal (Horizontal flue).

1200

 

From a terminal facing a terminal (Vertical flue).

600

L

From an opening in carport (e.g. door, window)

 

 

into the dwelling.

1200

M

Vertically from a terminal on the same wall.

1500

N

Horizontally from a terminal on the same wall.

300

R

From adjacent wall to flue (vertical only).

300

S

From an adjacent opening window (vertical only).

1000

T

Adjacent to windows or openings on pitched and flat roofs

600

U

Below windows or openings on pitched roofs

2000

1In addition, the terminal should be no nearer than 150 mm to an opening in the building fabric formed for the purpose of accommodating a built-in element such as a window frame.

2Only ONE 25mm clearance is allowed per installation. If one of the dimensions D, E, F, G or H is 25mm then the remainder MUST be as shown in brackets, in accordance with B.S.5440-1.

NOTE: The distance from a fanned draught appliance terminal installed parallel to a boundary may not be less than 300mm in accordance with the diagram below

 

300 min

Terminal

 

*

Assembly

 

 

 

 

 

 

 

Plume

Displacement Kit

Top View Rear Flue

Fig. 17

Property Boundary Line

J,K

T

Air Inlet

 

 

 

U

7.0Site Requirements

7.8Flue

NOTE: Due to the nature of the boiler a plume of water vapour will be discharged from the flue. This should be taken into account when siting the flue terminal.

1.The following guidelines indicate the general requirements for siting balanced flue terminals. For GB recommendations are given in BS 5440 Pt 1. For IE recommendations are given in the current edition of I.S. 813 “Domestic Gas Installations”.

2.If the terminal discharges onto a pathway or passageway, check that combustion products will not cause a nuisance and that the terminal will not obstruct the passageway.

3.If a terminal is less than 2 metres above a balcony, above ground or above a flat roof to which people have access, then a suitable terminal guard must be provided.

4.* This dimension may be reduced to 25mm by the use of Flue Deflector Kit part no. 5111068.

IMPORTANT:

Under car ports we recommend the use of the plume displacement kit.

The terminal position must ensure the safe and nuisance - free dispersal of combustion products.

IMPORTANT: If fitting a Plume Displacement Flue Kit, the air inlet must be a minimum of 150mm from any opening windows or doors (see Section 9.0).

Opening Window or Door

150mm

Fig. 18a

MIN.

 

R N

M

I I

F B

L

A

G

I

Likely flue positions requiring a flue terminal guard

D

 

A

C E

 

 

I

S

I

 

 

 

F

J,K

 

A

 

H H

Fig. 18

20© Baxi Heating UK Ltd 2012

Image 20
Contents Installation & Service Instructions Natural Gas Benchmark SchemeInstaller Notification Guidelines Scheme Members onlyCodes of Practice refer to the most recent version Important Installation, Commissioning, Service & RepairLegislation Safe Manual Handling GeneralPreparation TechniqueContents Description Contents of PackIntroduction General Layout LayoutExpansion Vessel Automatic Air Vent Circulation Pump Drain Off PointCentral Heating Mode Fig Domestic Hot Water Mode FigFrost Protection Mode Appliance OperationTechnical Data Gold Combi 24, 28 & 33 HE aDimensions and Fixings System Details InformationCentral Heating Circuit BypassExpansion Vessel Central Heating only Safety Pressure Relief Valve FigSystem Filling and Pressurising Fig Hard Water Areas Domestic Hot Water Circuit FigShowers Site Requirements LocationClearances Figs At leastSite Requirement Ventilation of CompartmentsGas Supply Electrical SupplyPer Pipe run Minimum FallPer Metre Run500mm min Minimum Fall50mm per Run Minimum fallPlume Displacement Kit FlueBelow windows or openings on pitched roofs 2000 Likely flue positions requiring a flue terminal guardFlue Options Total equivalent length = +B+C+2x90BendsTotal Equivalent Length = +B+C+1x90Bend Telescopic Flue inc. elbow Flue AccessoriesKey Accessory Size Code No Air Duct Connection Flue Duct Connection Boiler Adaptor Twin Flue Duct AdaptorTwin Flue Connection Flue Dimensions For Roof TerminalsFlue Trim Terminal Guard FigPlume Displacement Plume Displacement Kit Fig28/33 Determining Permissible LengthsExample Elbow30mm 50mmGeneral Fitting Notes Elbow to allow the flue to be installed as shown 60Ø extension piece. It must be secured using twoUsing a suitable bit e.g mm, drill through Extension and outlet. Secure using two of the screwsInstallation Unpacking & Initial PreparationFlushing After considering the site requirementsFitting the Filling Loop Kit Fitting the Safety Pressure Relief Discharge Pipe Fig Fitting The BoilerCondensate Drain see section Tighten all the connectionsFitting The Flue Wall Thickness Flue ElbowEnsure Elbow is fully engaged into Boiler Adaptor Wall Thickness Waste FlueEnsure Extension is fully engaged into Boiler Adaptor Inner Flue Support Bracket25mm Extension Cut End Terminal Block Cover Cable Clamp Making The Electrical ConnectionsPreliminary Electrical Checks Selector Switch Display CommissioningCommissioning the Boiler Screw Pump Automatic Air VentTemperature Control Selector Switch Display Temperature Control Gas Pressure Test Point Gas ValveCheck the Operational Working Gas Inlet Pressure It is necessary to set the boiler to ‘Calibration Mode’Setting the Timer Case Front Panel Facia Panel CompletionCompletion Annual Servicing Inspection Servicing13 .1 Annual Servicing Electrode Position 10 ±1Spark and Sensing Electrodes Fig Changing ComponentsIgniter Fig Fan Fig Venturi FigInjector Fig Gasket Venturi Injector Cover Gas Inlet Pipe Fan CollectorExtension Piece Burner FigInsulation Fig Central Heating Temperature Sensor NTC Fig Safety Thermostat FigDHW Temperature Sensor NTC Fig Flue/Heat Exchanger Thermostat Sensor FigAutomatic Air Vent Fig Pump Head Only FigPump Complete Fig Pressure Relief Valve Fig Pressure Gauge FigsHall Effect Sensor Fig Diverter Valve Motor Unit & Assembly Fig Plate Heat Exchanger FigSelector Switch Fig 14.22 P.C.B. FigGas Valve Fig Expansion Vessel FigSetting the Gas Valve Setting the Gas Valve CO2 checkFlue Adaptor Test Point Plug Analyser Probe CO2 should be 8.4% ± Reduce CO2Illustrated Wiring Diagram ElectricalShort Parts List Short Parts List426 315316 311 404419 422 400 415Error Codes Fault FindingInitial Fault Finding Checks Error 133 flashing Go to section ‘A’ Turn the selector switch toReset position for 5 seconds Pump runsError 133 flashing Go to section ‘I’ Turn Domestic Hot WaterOpen DHW tap fully Close DHW tapPCB X3 connector terminals 3 Switch terminalFan jammed or faulty winding Replace PCB Replace waterCheck wiring Viewing Window Replace sensor or PCB E28Gas at burner Replace gas valveReplace sensor Replace safety thermostatReplace PCB Is there 230V at Pages for Notes Pages for Notes GAS Boiler System Commissioning Checklist Service Record Potterton