Potthof & Co 24kw, 33kw, 28kw manual Initial Fault Finding Checks, Error Codes

Page 54

NOTE: When instructed to turn the selector to the reset position turn the selector switch fully anticlockwise against the spring pressure to the reset position and hold for 5 seconds to reset the boiler.

Table Of Error Codes

E20 Central Heating NTC Fault

E28 Flue NTC Fault

E50 Hot Water NTC Fault

E110 Safety Thermostat Operated

E119 Water Pressure Switch Not Operated

E125 Circulation Fault (Primary Circuit)

E130 Flue NTC Operated

E133 Interruption Of Gas Supply or Flame Failure

E160 Fan or Fan Wiring Fault

E193 Pre-Circulation Fault

18.0Fault Finding

18.1Initial Fault Finding Checks

1.Check that gas, water and electrical supplies are available at the boiler.

2.Electrical supply = 230V ~ 50 Hz.

3.CH water system pressurised to 0.5 bar minimum when the boiler is cold.

4.The preferred minimum gas pressure is 20 mbar.

5.Carry out electrical system checks, i.e. Earth Continuity, Resistance to Earth, Short Circuit and Polarity with a suitable meter.

NOTE: These checks must be repeated after any servicing or fault finding.

6.Ensure all external controls are calling for heat and check all external and internal fuses. Before any servicing or replacement of parts, ensure the gas and electrical supplies are isolated.

18.2Error Codes

1.If a fault occurs on the boiler an error code may be shown by the facia display.

2.The codes are either two or three digit, preceded by the letter 'E'. For example, code E133 will be displayed by 'E1' alternating with '33'. E50 is shown as 'E' then '50'

E20, E28 & E50 indicate faulty or incorrect components.

E110 shows overheat of the primary water and E130 overheat of the flue system.

E119 is displayed when the primary water pressure is less than 0.5 bar.

E133 indicates that the gas supply has been interrupted, ignition has failed or the flame has not been detected.

E125 is displayed in either of two situations:-

i)If within 15 seconds of the burner lighting the boiler temperature has not changed by 1°.

ii)If within 10 minutes of the burner lighting the boiler temperature twice exceeds the selected temperature by 30°. In these instances poor primary circulation is indicated.

3.By turning the selector switch to the 'Reset' position for a minimum of 5 seconds when E110, E130 & E133 are displayed it is possible to relight the boiler.

4.If this does not have any effect, or the codes are displayed regularly further investigation is required.

54© Baxi Heating UK Ltd 2012

Image 54
Contents Installation & Service Instructions Natural Gas Benchmark SchemeInstaller Notification Guidelines Scheme Members onlyImportant Installation, Commissioning, Service & Repair LegislationCodes of Practice refer to the most recent version Preparation Safe Manual HandlingGeneral TechniqueContents Contents of Pack IntroductionDescription Expansion Vessel Automatic Air Vent General LayoutLayout Circulation Pump Drain Off PointFrost Protection Mode Central Heating Mode FigDomestic Hot Water Mode Fig Appliance OperationTechnical Data Gold Combi 24, 28 & 33 HE aDimensions and Fixings Central Heating Circuit System DetailsInformation BypassSafety Pressure Relief Valve Fig System Filling and Pressurising FigExpansion Vessel Central Heating only Domestic Hot Water Circuit Fig ShowersHard Water Areas Clearances Figs Site RequirementsLocation At leastGas Supply Site RequirementVentilation of Compartments Electrical SupplyPer Metre PerPipe run Minimum Fall RunMinimum Fall 50mm per500mm min Run Minimum fallBelow windows or openings on pitched roofs 2000 Plume Displacement KitFlue Likely flue positions requiring a flue terminal guardFlue Options Total equivalent length = +B+C+2x90BendsTotal Equivalent Length = +B+C+1x90Bend Flue Accessories Key Accessory Size Code NoTelescopic Flue inc. elbow Twin Flue Duct Adaptor Twin Flue ConnectionAir Duct Connection Flue Duct Connection Boiler Adaptor Flue Trim Flue DimensionsFor Roof Terminals Terminal Guard FigPlume Displacement Plume Displacement Kit FigExample 28/33Determining Permissible Lengths Elbow50mm General Fitting Notes30mm Using a suitable bit e.g mm, drill through Elbow to allow the flue to be installed as shown60Ø extension piece. It must be secured using two Extension and outlet. Secure using two of the screwsFlushing InstallationUnpacking & Initial Preparation After considering the site requirementsFitting the Filling Loop Kit Condensate Drain see section Fitting the Safety Pressure Relief Discharge Pipe FigFitting The Boiler Tighten all the connectionsEnsure Elbow is fully engaged into Boiler Adaptor Fitting The FlueWall Thickness Flue Elbow Wall Thickness Waste FlueInner Flue Support Bracket 25mm Extension Cut EndEnsure Extension is fully engaged into Boiler Adaptor Making The Electrical Connections Preliminary Electrical ChecksTerminal Block Cover Cable Clamp Commissioning the Boiler Selector Switch DisplayCommissioning Screw Pump Automatic Air VentCheck the Operational Working Gas Inlet Pressure Temperature Control Selector Switch DisplayTemperature Control Gas Pressure Test Point Gas Valve It is necessary to set the boiler to ‘Calibration Mode’Setting the Timer Completion CompletionCase Front Panel Facia Panel Servicing 13 .1 Annual ServicingAnnual Servicing Inspection Electrode Position 10 ±1Changing Components Igniter FigSpark and Sensing Electrodes Fig Injector Fig Fan FigVenturi Fig Gasket Venturi Injector Cover Gas Inlet Pipe Fan CollectorBurner Fig Insulation FigExtension Piece DHW Temperature Sensor NTC Fig Central Heating Temperature Sensor NTC FigSafety Thermostat Fig Flue/Heat Exchanger Thermostat Sensor FigPump Head Only Fig Pump Complete FigAutomatic Air Vent Fig Pressure Gauge Figs Hall Effect Sensor FigPressure Relief Valve Fig Diverter Valve Motor Unit & Assembly Fig Plate Heat Exchanger FigSelector Switch Fig 14.22 P.C.B. FigGas Valve Fig Expansion Vessel FigFlue Adaptor Test Point Plug Analyser Probe Setting the Gas ValveSetting the Gas Valve CO2 check CO2 should be 8.4% ± Reduce CO2Illustrated Wiring Diagram Electrical426 Short Parts ListShort Parts List 315316 311 404419 422 400 415Fault Finding Initial Fault Finding ChecksError Codes Reset position for 5 seconds Error 133 flashingGo to section ‘A’ Turn the selector switch to Pump runsOpen DHW tap fully Error 133 flashing Go to section ‘I’Turn Domestic Hot Water Close DHW tapFan jammed or faulty winding Replace PCB PCB X3 connector terminals 3Switch terminal Replace waterGas at burner Check wiring Viewing WindowReplace sensor or PCB E28 Replace gas valveReplace safety thermostat Replace PCB Is there 230V atReplace sensor Pages for Notes Pages for Notes GAS Boiler System Commissioning Checklist Service Record Potterton