2.Connect the circulating water by connecting one line to the circulating pump outlet line (3/8” barb) and clamp in place. Connect the other line to the bulkhead return fitting located by the agitator motor (3/8” barb) and clamp in place.

3.Connect the conduit lines. Two (2) carbonated water lines and two (2) product output lines (#1 regular rootbeer & #2 diet rootbeer)

CONNECTING SUPPLY LINES

Braided CO2

Gas Line

Black Water

Supply Line

Color Coded

Syrup Lines

Connect water supply inside unit.

Water Supply & Regulator

Pre-installation of towers is required and the appropriate syrup supply must be connected to the corresponding tower.

Proceed with the Following Tests

Ensure that overflow tube is firmly seated, not leaking.

Check conduit for proper support and insulation.

Cycle carbonator “A” momentarily.

Cycle circulating Motor “A” momentarily.

Cycle compressor momentarily.

Ensure that agitator motor is running.

Ensure that ice bank control probe is securely attached to evaporator coil.

Connect CO2 supply inside unit.

CO2 Supply & Gauge

Connecting conduit at the refrigeration unit

1.Connect the product lines either from the bag-in-box or tank (#1 regular rootbeer & #2 diet rootbeer). See the plumbing diagrams for the tower setup that pertains to your installation.

2.Insert the Multipar conduit into the outlet opening on the left hand side of unit. Conduit insulation must extend inside of opening in unit for proper operation of equipment.

Insulated

Beverage

NOTE: Multipar conduit is color coded for easy identification of lines. When making connections always attach lines requiring the longest connection from the insulation first. The remaining lines can be trimmed as required to make the routing neat and secure.

3.Locate the two blue carbonated water lines of the Multipar conduit. Attach one of the blue lines to the tee fitting located on top of the carbonator tank. Attach the other blue line to John Guest elbow fitting on the stainless coil labeled “8”.

4.Locate the black plain water line of the Multipar conduit. Attach this line to the elbow fitting on the stainless coil labeled “W”.

5.The remaining lines of the Multipar conduit are syrup supply lines and must be attached to the appropriate elbow fittings on stainless steel syrup coils. Note the numbered lines attached to the opposite end of each syrup coil when making connections.

Part Number 020001552 5/11

2-13

Image 23
Contents America’s Quality Choice in Refrigeration Installation, Use & Care ManualModel 11M Root Beer System Refrigeration Unit PERSONAL INJURY POTENTIAL Safety NoticesProcedural Notices Read These Before ProceedingSpecifications Table of Contents continued SectionSection Installation Attention Marine InstallationsConnecting Insulated Conduit Table of Contents continuedEquipment Placement Tower InstallationBag-In-BoxSystem Sanitation Table of Contents continued Section MaintenanceSection Before Calling for Service Beverage System CleaningTHIS PAGE INTENTIONALLY LEFT BLANK Read This Manual How to Read a Model NumberSection General Information SectionSpecial Applications AccessoriesSpecifications ATTENTION MARINE INSTALLATIONSSerial Plate Location Warranty InformationTHIS PAGE INTENTIONALLY LEFT BLANK UNPACKING AND INSPECTING Section InstallationKit assembly includes GeneralSide View InstallationDimensions and Clearances Top ViewBLADE TOWER REMOTE CONDENSERSafe Installation Dos and Don’ts REQUIREMENTS FOR POST MIX UNITS Location RequirementsCLEARANCES RATINGSAmbient Location Requirement Installer InstructionsSPECIFICATIONS ElectricalGROUNDING INSTRUCTIONS Drain Hose Connection Plumbing/Water SupplyPLUMBING POTABLE WATER PLUMBING REQUIREMENTS - GENERALSingle Tower Plumbing PLUMBING CIRCUIT DIAGRAMS - MODEL 11M ROOT BEERModel 11M Root Beer Dual Tower Plumbing 2-10Model 11M Root Beer Three Tower Plumbing 2-11CONNECTING INSULATED CONDUIT Refrigeration Unit InstallationEQUIPMENT PLACEMENT TOWER INSTALLATIONProceed with the Following Tests CONNECTING SUPPLY LINESConnecting conduit at the refrigeration unit 2-13PROPER USE OF JOHN GUEST FITTINGS Proper John Guest Fitting InstallationConnect the drain 2-14Control Switches 2-15Model 11M Connections INSULATING CONNECTIONS Condenser and Pre-chargedLines InstallationAeroquip Connection 2-16PRE-CHARGEDREFRIGERATION LINE REQUIREMENTS INSTALLING THE MULTIPLEX REMOTE CONDENSER2-17 2-18 CONNECTING THE PRE-CHARGED REFRIGERATION LINESTESTING CO2 CIRCUIT FOR LEAKS TESTING SYRUP CIRCUIT 5 GALLON TANKS ONLYBUILDING AN ICE BANK Start-UpPreparing Ice Bank 2-19Check the water bath for full ice bank Installation Checklist2-20 Observe the pump operations for leaksWater Filters Section OperationOperation Typical SystemSequence of Operation WATER BATH ACCESSSERVICE ACCESS How the Multiplex WorksStart-up Equipment Setup and Close ProcedureEQUIPMENT SETUP PROCEDURE EQUIPMENT CLOSE PROCEDURETHIS PAGE INTENTIONALLY LEFT BLANK Sanitizing Section MaintenanceMaintenance BEVERAGE SYSTEM CLEANINGFIGAL BEVERAGE SYSTEM Shipping, Storage and Relocation Back-flowPreventer MaintenanceTHIS PAGE INTENTIONALLY LEFT BLANK Checklist Section Before Calling for ServiceBefore Calling for Service THIS PAGE INTENTIONALLY LEFT BLANK Before Calling for ServiceSection Page Part Number 020001552 5/11