STEP I
insert short and long spacer (29 & 24) in pro per location on shaft. Press rear bearing (20) on to shaft.
STEP II
Insert shaft through rear housing bore through gear. Drive front bearing into place against gear.
STEP III
Press bearing cups into both front and rear bores.
STEP IV
Bolt front cap (4) in place using same shim pack present wh en disassembled. Bolt rear cap (21) in place using
same shim pack also.
STEP V
Check bearing preload and gear back lash. Gear back lash should be.015” to .025”. If back lash is tight add
shim to front cap and re move sh im from re ar ca p. Reve rse p roce dure if b ack lash is to lar ge. Check input sh aft
preload - push and pull on shaft to see if end play exists and if so remove shim from back cap (21). The only
method to measure preload is to rotate input shaft turning whole box and reading should be 30-50 in/lbs.
STEP VI
Remove front and rear caps, apply gasket sealant, and reinstall caps and torque bolts to required torque,
Recheck using torque step 5.
STEP VII
Press input shaft seal (6) into front cap (4). Install top cover (26) with gasket (31). Gearbox is ready to fill with
oil.
NOTE: Be sure seal plate (34) is installed using capscrew (33). Failure to install plate could result in seal