MGE Galaxy 5000
Parallel UPS
Figure 2-15: Routing the Control/Communications Cables for Parallel UPS
Separate the control and communication cables from the power cables.
Run the cables together in front of the protection panels and tie them to the panels as indicated.
Free slots for optional communication cards. See installation drawing for proper card placement.
Slot for relay communications card
Ties
Ties
Cable description | Insulation level | Location on illustration |
|
|
|
External bypass cabinet cable | ELV | 1 |
|
|
|
CAN cables | SELV | 1 |
|
|
|
| SELV | 1 |
|
|
|
Relay communication card | SELV | 3 |
|
|
|
Optional communication card | SELV or LV | 4 |
|
|
|
External battery | SELV | 6 |
|
|
|
| SELV | 7 |
|
|
|
CAUTION To ensure sufficient isolation of
2 — 12 | Setup and Installation |